01.06.2021

Project organization of construction. Project organization of construction Transport scheme


Quality projects of the village with coordination
——

Leave an application for a free & niss specialist and get a preliminary calculation of the value of & NBSPOs & NBSP project

To get the consultation

    Depending on the complexity of the object, the conditions for conducting construction work and socio-economic significance, items can be added, expanding, have a more unfolded structure.

    In the staff, such aspects of construction and installation work, such as logistics, must be noted.

  • safety and safety of labor;
  • natural and climatic conditions;
  • technical equipment;
  • compliance with the norms of nature conservation;
  • providing the object with communications and much more.

Only the deep knowledge of the specifics of the construction, repair and installation work, accompanying their documents and regulations, can ensure the compilation of a competent detailed design of the construction organization. And on this base, other documents, permits and tolerances will be formed. So, in particular, the project manufacturing project (PPR) is built on the basis of the PIT and contains, in fact, a step-by-step plan for working on each site of the object.
Thus, the construction organization project is a mandatory document, both for a contractor and for the customer, and for organizations that provide logistics in the construction facility that need to coordinate the parties and the final approval of state expertise.

We carry out the development of the PIC for construction work and laying engineering communications:

  • explanatory note
  • stroyenplane for the preparatory period
  • explanatory note
  • calendar work schedule
  • strogenpalan for the main period of work

14 years of successful work

More than 140 projects in 9 cities throughout Russia

Development of PAT for industrial facilities of any complexity

Coordination of projects

Maintenance of the PIC in the examination and the Glavgosexpertization

Any construction of reliable, harmonious buildings and structures requires careful engineering calculation and professional planning of material, technical and labor costs. In accordance with the requirements of the legislation, the project documentation project includes a construction organization project. The significance of the PM emphasizes the fact that this document is subject to state expertise, on the basis of the decision of which is issued a permit for the construction of a fixed in the post.

Unlike a project for the production of works developed on certain construction facilities, the project organization of work covers the entire complex of buildings and structures at the construction site. Based on the master plan, several PPR are drawn up, in which the technological process is discussed in detail, the rational organization of construction and the expenditure of material and technical and labor resources for the construction of a specific object. Construction organization projects are developed as for entire residential microdistricts with a variety of infrastructure, large production complexes and for individual buildings and structures. The elements are necessary in the event that it is planned to consolidate or reconstruct objects. The construction project project is a mandatory document for the customer, contracting organizations, and organizations responsible for financing and logistical support for construction.

Examples of completed projects

Reconstruction of OJSC NK Rosneft

Moscow, Enthusiast Highway, D.40

The project of the construction organization (pos) as part of the project of the reconstruction of OJSC NK Rosneft - MZ "Petroleum Product" with the construction of a complex for the production of lubricants and special liquids with a total capacity of 31 000T / year (second queue).

Housing and accommodation with built-in kindergarten and underground parking

Moscow, Kozhevnichesky Travel, Property 4, P.1, 2, 3, 4, 5, 6, 6a, 6b, 7, 8, 9, 10

The project of the construction organization (pos) of the housing and hotel complex with a built-in kindergarten and underground parking on the land plot with cadastral number 77: 01: 0006018: 93, with an area of \u200b\u200b16037 sq.m.

Complex reconstruction of objects of the FGBU "Joint Sanatorium" Sochi "

Krasnodar Territory, Schochi, grape st., 27

Project organization of construction under the object "Complex reconstruction of facilities of the FGBU" Joint Sanatorium "Sochi" of the Office of the President of the Russian Federation. Third queue - auxiliary objects (reconstruction). " Adjustment-2.

Pos first stage of residential building

Moscow region, northwestern part of MKR. Novogorsk (Khimki, pos. Ivanovskoye)

Draft organization of construction (pos) 1st stage of an apartment building in the territory of Khimki district.

Reconstruction of the stadium for 3000 people

Moscow Region, Proprevka

Project organization of construction for the reconstruction of the stadium with a stand of up to 3000 viewers of the municipal autonomous institution of sports of the sports and recreation complex "Melody"

Strogenpalan for the main construction period

Moscow, Cao, B.Kozikhinsky per., 25

Construction plan for the main period of construction of a residential building with built-in non-residential premises and an underground parking lot

Features of the development of the village

  • residential buildings;
  • in winter;
  • in mountainous areas;

Our design certificates

What will you receive by contacting us to develop a construction organization project:

Skilled,
Properly executed project or construction plan

Deadlines
Performing work

Attention to detail
and interest

Consultation
on the development of pos and other documents

Need high-quality pos?

Get the calculation of the project and consultation of a specialist

An example of a project that has passed expertise

Positive conclusions of the Mosororexpertzes on the village of Living Development TD "Volynskaya", in the composition of 2 and 3 construction days (Moscow, ZAO, Minsk ul)

Positive conclusions of Mosorcorexpertzes on the village of residential buildings with underground parking (hull 3,4,6, Moscow, ZAO, Volokolamskoye highway, VL67)

Positive conclusion of an examination of a high-rise complex with an underground garage (Moscow, Svao, Pr-d Serebryakova, Vl.11-13)

Positive conclusion of an examination of the high-functional residential complex (Moscow, Goljanovo, Amur Str., Vl.3)

POS (Moscow, ul.protnaya, Vl.6)

Positive conclusion of the examination of POS (Moscow, Cao, coursework per., Vl.10 / 1)

Source materials for project development

The staff are developed on the basis of the following source materials:

  • Section Architectural solutions (AR);
  • Section constructive solutions (CR);
  • A tough;
  • The results of engineering and geological surveys;
  • Technical and economic indicators (TEP) of construction;
  • Solutions for the use of materials, machinery and resources;
  • Information on the supply of building materials and equipment;

Features of the development of the village

The construction project project provides organizational and technical preparation for construction and justifies the timing and order of delivery of objects.

Based on engineering calculations (with the reconstruction of facilities - on the basis of technical examination materials) and the necessary project documentation in the staff, the total amounts of capital investments and construction and installation works are calculated indicating the time of execution, the need for the necessary working personnel, taking into account their qualifications and the need for material- technical resources. The village must contain information about:

  • solving the problems of organizing transport, water supply, sewage, power supply, communications;
  • places of export (or shipment) of extra (or missing) soil, export of construction garbage;
  • controlling the quality and safety of construction and installation works, labor protection and environmental organization;
  • construction in complex climatic conditions - at low (high temperatures), in mountainous areas, on soils having special properties;
  • activities to fulfill work by the Watch method, including work schedules, labor and recreation, composition and technical equipment of the brigades;
  • used machines, mechanisms, technological inventory and mounting equipment;
  • schemes of storage and lines of goods, etc;

The composition, as well as the POS content may vary depending on the characteristics of a particular object, the specifics of the work conditions or delivery of materials, as well as other aspects of construction. When erecting simple objects, a reduced version of the PPR can be used.

Objects requiring a special approach to the construction work are listed below:

  • residential buildings;
  • buildings that will be used to provide household services to the population;
  • main car or railways, gas and oil pipelines, power lines and communication;
  • water or hydraulic objects;
  • enterprises specializing in mining, other objects.

The feature of the conditions under which construction is carried out also plays a considerable role during the design of the PIC. Features in drafting documentation are defined for objects that are built:

  • in winter;
  • on soils having special properties;
  • in mountainous areas;
  • in special natural conditions.

The area of \u200b\u200bconstruction, its features, the complexity of the work performed - the parameters that have the main impact on the content of the PPR and PIT.
The complexity of the design of the design of the construction organization depends on a specific object, its scale and specificity. The specialists of the company are offered their services to create projects of any complexity from a small cottage to a large hydraulic or industrial complex. High qualifications, rich work experience and operational solution of tasks - a guarantee of successful cooperation with the company POSTROY.

The text part should contain:

  • characteristic of the region at the location of the object of capital construction and conditions of construction;
  • evaluation of the development of transport infrastructure;
  • information on the possibility of using the local labor force in the implementation of construction;
  • a list of activities to attract for the construction of qualified specialists, including to carry out work by the Watch method;
  • characteristics of the land plot provided for construction, justification of the need for use for the construction of land outside the land plot provided for the construction of an overhaul object;
  • a description of the features of the work in the conditions of the current enterprise, in the location of underground communications, power lines and communication - for production facilities;
  • description of the features of the work in the conditions of cramped urban development, at the locations of underground communications, power lines and communication - for non-production facilities;
  • the rationale for the adopted organizational and technological scheme, which determines the sequence of the construction of buildings and structures, engineering and transport communications, ensuring compliance with the construction of deadlines established in the calendar plan (its stages);
  • a list of types of construction and installation work, responsible structures, sections of engineering and technical support networks to be examined with the preparation of appropriate acts of acceptance before the production of subsequent works and the device of subsequent structures;
  • technological sequence of work when erecting capital construction objects or their individual elements;
  • substantiation of the needs of construction in personnel, main building machines, mechanisms, vehicles, in fuel and fuel and lubricants, as well as in electrical energy, pair, water, time buildings and structures;
  • justification of the size and equipment of sites for storing materials, structures, equipment, enlarged modules and stands for their assembly. Solutions for the movement of heavy oversized equipment, enlarged modules and building structures;
  • proposals for ensuring the quality control of construction and installation work, as well as supplied to the site and mounted equipment, structures and materials;
  • proposals for the organization of the GEODESIC and Laboratory Control Service;
  • the list of requirements to be taken into account in the working documentation developed on the basis of project documentation, in connection with the methods of building construction structures and equipment installation methods;
  • justification of the need for housing and socio-domestic service personnel involved in construction;
  • a list of activities and design solutions for the definition of technical means and methods of work that ensure the implementation of regulatory requirements for labor protection;
  • description of design solutions and environmental protection measures during the construction period;
  • justification of the duration of the construction of the capital construction object and its individual stages;
  • the list of measures to organize monitoring for the state of buildings and structures located in the immediate vicinity of the facility under construction, earthlings, construction, assembly and other works on which may affect the technical condition and reliability of such buildings and structures;

Graphic PA should contain:

Thus, a large number of subject PPRs of the most diverse sense are based on information taken from the village. Starting construction and installation work, without having a stagnant examination in the prescribed manner prohibited by law. Project documentation will be needed not only to the investor, customer of construction, but also contracting for construction organizations.

Depending on the complexity of construction, the development of the pos is produced in one or two stages - the Stage "Project" (P) and the Stage "Working Documentation" (P).

StroyPlan.
Strogenpalan - a substantial part of the project POS. It can be seen as well as functionally and rationally organized zones of storage of materials and raw materials, household, administrative, sanitary facilities, temporary roads are placed. All hazardous zones and methods for their elimination are also shown on the buildingplane, the location and work of the main mechanisms, their interaction and joint work are shown.

Calendar plan
The calendar plan or schedule is a document that clearly defines the duration, order and combining the performance of work with the indication of the financial costs of construction in stages, for the PPR, is specified for the PPR. This document is undoubtedly one of the objective and timely financing of objects in the organization of competent and timely financing. Also, the calendar graph provides the dependence of construction from local natural and climatic conditions, while finding an object in difficult conditions.

Explanatory note
An explanatory note is an equally important element of construction organization projects. From the explanatory note, you can get a detailed representation of all the features of the conditions of the upcoming construction, as well as about its sequence, methods and technology for the production of construction and installation work, quality control and other processes necessary in the construction. Also, the explanatory note produces all calculations necessary to determine the needs of construction in providing labor resources, engineering, etc.

Regulatory framework for the development of pos

The construction refers to the area of \u200b\u200bactivity in which the requirements for the documentation are particularly strict, they are justified on numerous standards, joint ventures, discs and rules. One of the main documents, the mandatory availability of which was approved in the SP 48.13330.2011, is the PPR - a project for the production of work.

The federal legislation of the Town Planning Code of the Russian Federation regulates the need to develop pos. According to him, the beginning of work in the field of capital construction is unacceptable without the presence of project documentation, to which the construction project is related. The development of the PIT section is carried out in accordance with the SSP48.13330.2011 and with the Decree of the Government of the Russian Federation No. 87 of February 16, 2008.

Coordination of projects

The process of coordination is regulated by "Instruction on the composition, the procedure for the construction, coordination and approval of design and estimate documentation for the construction of enterprises, buildings and structures" SNiP 1.02.01-85, as well as departmental construction regulations. In accordance with these documents, the Customer conducts coordination with the General Contracting Construction and Assembly Organization.

In addition, a number of examinations and coordination of the village are held with other supervisory authorities, the complete list of which depends on the specifics of the object: architecture management; prefectures of administrative units; Department of Glavgosexpertiza; sanitary supervision; Department of fuel and energy economy; Department of Economic Policy; Office of urban transport and other organizations.

We develop projects:

Application for design

Cipher……………. -Pos

1 text part General data

The name of the object, its purpose, location;

Print information about design solutions.

The list of regulatory documentation is presented, on the basis of which the pos.

2 Brief characteristic of the district and construction conditions

The subsection indicates the physico-geographical characteristics of the site of construction, climate, engineering and geological and hydrological conditions (necessarily indicates the level of groundwater).

3 Evaluation of the development of transport infrastructure

It is necessary to indicate the level of development of the transport network, the station of unloading, career, waste disposal locations.

4 Information on the possibility of using local labor in the implementation of construction

Information about the presence or absence of the possibility of using the local labor force is presented.

5 List of measures to attract qualified specialists to carry out construction, including to perform work by the Watch method

Requirements for contracting organizations, to the staff attestation, directions of certification are indicated.

Information about the need for an organization (or no need) of the Watch method.

6 Characteristics of the land plot provided for construction. Justification of the need for use for the construction of land sites located outside the land plot provided for construction

This subsection provides a description of the land plot, designated for construction (on what lands it is in rental or owned by the Customer, the area of \u200b\u200bthe land plot).

Further indicates the need (or lack of necessity) use of an additional area to accommodate temporary buildings and structures, storage sites. In the presence of additional land plots, the area of \u200b\u200bthese sites is indicated, the characteristic, shows the location on the construction general plan or on the overview scheme.

7 Description of the features of work in the current enterprise, in places of underground communications, power lines and communication

For production facilities

A description of the features of the work in the conditions of the current enterprise is provided: a list of work on reconstruction (reorganization of workshops, expansion of buildings, structures) or technical re-equipment of enterprises, requirements for its work (without stopping production, with a partial or complete stop), an assessment of the effect of dismissal to choose methods of major construction work, justifying the means of mechanization used to perform these works.

In the case of work in places location of power lines, communications, security zones of oil, gas pipelines, water pipelines, their description and characteristics are given, the security and hazardous zones are determined, the conditions for the production of work are indicated, the need to develop relevant construction projects.

8 Description of the features of the work in the conditions of cramped urban development, in places of underground communications, power lines and communication

For non-manufacturing facilities

The description of the features of work in the context of the municipal urban development should consist of the characteristics of the constrained conditions, the determination of hazardous zones formed during the operation of lifting cranes, the instructions of objects entering the hazardous areas, from the rationale for measures to safely conduct work (restriction of test zones and reducing hazardous areas , device for protective structures (shelters), application of protective screens, platform fence, etc.).

The section includes:

-Stability of the installation and works of cranes near the slopes of the kittlers, measures to safely work several cranes;

- Mimmowns on the temporary closure of streets, to limit traffic.

In the case of work in places location of power lines, communication, security areas of oil, gas pipelines, water pipes, a description is carried out as for production facilities.

9 Justification of the adopted organizational and technological scheme, which determines the sequence of building buildings and structures, engineering and transport communications

The subsection presents the adopted technological scheme for the construction of construction (including the preparatory and the main period), the work carried out in the preparatory and main periods, the sequence of the construction of buildings and structures is indicated if the project provides for the construction of several buildings and structures.

10 List of basic types of construction and installation work, responsible structures, sections of engineering and technical support networks, subject to examination with the preparation of relevant acts of acceptance before the subsequent work and the device for subsequent structures

The list of responsible structures subject to survey may be made to ensure measures to ensure the construction of their strength and stability, as well as methods and means of performing their control and testing.

11.Che technological sequence of work when erecting objects

The technological sequence of works or their individual elements is determined according to the selected organizational and technological scheme of the construction of the object and organizational and technological schemes of the construction of the main buildings and structures.

The organizational and technological scheme of the construction of the capital construction object establishes the sequence of construction of basic objects, utility and maintenance facilities, external networks and structures.

Organizational and technological schemes of the construction of basic buildings and structures establish a sequence of erection of individual buildings (structures) in their parts (nodes, sections, tiers, floors, etc.).

For residential buildings, a sequence of the construction of the building itself, outdoor engineering networks, improvement is presented. The following is a description of all listed works.

The technological sequence of work, installed by organizational and technological schemes, is the source material for the development of the calendar plan.

An example of a description of the work provided for in the project

(This example is not universal. The workset is adjusted in accordance with the technical solutions adopted):

Excavation

Earthworks must be performed according to the rules.
SP 45.13330-2010 "Earth structures, grounds and foundations."

During the construction of a residential building, earthworks begin with removing the fertile layer of the soil in a non-murosle state with moving it in temporary dump outside the removal zone. The cutting of the fertile layer of soil and the movement of the fertile layer of the soil is made by transverse and longitudinal passages of the bulldozer.

The dump should be located at a distance not closer to 0.5 m from the edge of the trench being developed to avoid its squeezing. When removing, moving and storing a fertile soil layer, it is not allowed to mix it with mineral soil, pollution with liquids or materials, erosion and blowing, as well as its use for filling.

When developing a trench, the excavator must be beyond the prism of the soil collapse (sloping) at a distance indicated in Table 1.

Table (table number) - the smallest distance from the base of the slop to the nearest supports

Soil (not bulk) With the depth of the excavation, m
1,00 2,00 3,00 4,00
Table continuation
Sand and gravine 1,50 3,00 4,00 5,00
Supaudea 1,25 2,40 3,60 4,40
Loamy 1,00 2,0 3,25 4,00
Clayey 1,00 1,50 1,75 3,00
Lesova dry 1,00 2,00 2,50 3,00

When developing a trench by an excavator, the soil should be thrown away at a distance of at least 0.50 m on the brings of the trench (pit) in dry and related soils and at least 1.00 m in sand and moistened soils.

The trench with vertical walls without fastening is developed by a single-bonded excavator in the soils of natural humidity with an undisturbed structure in the absence of groundwater to the depth of no more:

In bulk sand and grave soils 1.00 m;

In sulesa 1.25 m;

In Suglinka and clays 1.50 m;

In particularly dense unknown soils of 2.00 m.

When digging trenches and recreation of greater depths, it is necessary to arrange the slopes of various embezzlement depending on the composition of the soil at the groundwater level below the depth of the excavation according to Table 2.

Table (table number) - permissible steepness of slopes of trenches

Soils Trench depth, m
Up to 1.50 1,50-3,00 3,00-5,00
angle of slope, degree bias angle of slope, degree bias angle of slope, degree bias
Bulk 56 1:0,67 45 1:1,00 38 1:1,25
Sandy and gravel 63 1:0,50 45 1:1,00 45 1:1,00
Spring 76 1:0,25 56 1:0,67 50 1:0,85
Loam 90 1:0,00 63 1:0,05 53 1:075

The development of trenches by a single-line excavator should be carried out with the elimination of scallops at the bottom in the digging process, which is achieved by pulling the bucket along the bottom of the trench after the development of a slaughter.

In the event of groundwater appearance, water-gravilization of incoming water from the watershedral (pit) followed by pumping the pump (piston, diaphragm or centrifugal, depending on the head of the incoming water) to the surface, where the water is removed from the drums or traders.

The soil in the pit is chosen without reaching the design mark - 10cm. The refinement of the soil is performed immediately before starting work on the foundation.

The soil for the inverse backfill of the trench sinuses and the pit is moved by a bulldozer 9 or automobiles from the reserve.

The backflow of trenches and sinuses should be made of mineral soil without construction debris, without inclusions of large debris (more than 50mm in diameter) of solid rocks (crushed stone, gravel, frozen closures) with layer-by-layer sealing pneumatic glasses and platforms.

Monolithic reinforced concrete work

The production of all types of work should be carried out in accordance with the PPR, the main provisions for the production of construction and installation work used in this project, and the requirements of the joint venture 70.13330.2012 "carrying and enclosing structures".

Concrete and a solution on the construction site is delivered to concrete mixers.

Concrete flow is carried out by concrete pump. Feeding formwork and reinforcement is provided by the truck.

Concrete mixtures should be laid in concrete structures with horizontal layers of the same thickness without breaks, with a sequential direction of laying in one direction in all layers.

When the concrete mixture is sealing, it is not allowed to support vibrators to fittings and mortgage products, heavy and other fastening elements. The depth of immersion of the deep vibrator in the concrete mixture should ensure its recess in the previously stacked layer by 5.00 - 10.00 cm. The step of rearrangement of the depths of the vibrators should not exceed the one-hour radius of their action, and the step of rearrangement of surface vibrators must provide overlap to 100.00 mm. The area of \u200b\u200bthe vibrator boundary of the already provincial plot.

The seal of the concrete mix depends on the duration of the vibration. The seal is considered sufficient if the sedimentation of the mixture is stopped, the separation of air bubbles is stopped, cement milk appears on the surface of the concrete structure.

In case of deformation or displacement of the formwork, concreting must be discontinued and the formwork is fixed before the establishment of concrete

In the initial period of hardening (up to 7 days), the concrete must be protected by a polymer film against atmospheric precipitation or moisture loss, subsequently, to maintain temperature and humidity regimen with the creation of conditions that ensure the increase in its strength.

During the rain, the concrete plot should be protected (by a polymer film, light mobile canopies, tarpaulin, etc.) from water to the concrete mix. Concrete, blurred rain should be removed.

The hardening concrete should be protected from mechanical damage.

Laying the next layer of the concrete mix is \u200b\u200ballowed before the selection of the concrete of the previous layer. The duration of the interruption between the laying of the adjacent layers of the concrete mix without the formation of the workshop is established by the construction laboratory. The top level of the laid concrete mix should be 50-70 mm below the top of the formwork shields

The quality of concrete stacked in the formwork is controlled by sampling the concrete mixture.

Control concrete samples must be selected in accordance with Table 4 GOST 10180-90 "Concretes. Methods for determining the strength of control samples. " The strength of the cubes should be carried out under conditions corresponding to the hardening conditions of concrete in the formwork.

Control cubes should be tested at 7 and 28 - daily age.

In the process of performing work, it is necessary to make data on concreting and control into special journals.

Concrete care measures, the order and timing of their conduct, control over their implementation and the timing of the structures of structures should be established by the PPR.

Reinforcement steel (rod, wire) and varietal hire, reinforcement and mortgage elements must comply with the project and requirements of the relevant standards. The dismemberment of spatial large-sized reinforcement products, as well as the replacement of the stipulated reinforcement steel should be coordinated with the customer and the design organization.

Transportation and storage of reinforcement steel should be performed according to GOST 7566-94 *.

The billet of the rods of dimensional length from the rod and wire fittings and the manufacture of unknown reinforcement products should be performed in accordance with the requirements of SNIP 3.09.01-85, and the manufacture of reinforcing frameworks from the rods with a diameter of more than 32.00 mm, rolling profiles - according to section 8 SP 70.13330- 2012.

The manufacture of spatial large-sized reinforcement products should be produced in assembly conductors.

The workpiece (cutting, welding, formation of anchor devices) and the installation of the reinforcement should be performed according to the project in accordance with SNiP 3.09.01-85.

Installation of reinforcement structures should be made mainly from large-sized blocks or unified grids of factory manufacture with securing the protective layer.

Installation on the reinforcement structures of pedestrian, transport or mounting devices should be carried out in accordance with the PPR, in coordination with the project organization.

Rods of rods should be made:

butt - peaks or crimping sleeves and screw couplings with the equalization of the junction;

cross-shaped - viscous annealed wire. It is allowed to use special connecting elements (plastic and wire locks).

Button and cross-shaped welded connections should be performed on the project in accordance with GOST 14098-91.

When the monolithic sections device in winter, the maintenance of concrete is performed by the electrical heating method. The electrical heating zone should be under the clock supervision of duty electricians.

The acceptance of the completed concrete and reinforced concrete structures or parts of structures should be issued in the prescribed manner as an act of examining hidden works or act on acceptance of responsible structures.

Installation of precast concrete structures

Installation of precast concrete structures must be carried out according to SP 70-13330-2012 "Bearing and enclosing structures"

Delivery of precast concrete blocks is carried out by the sidewall of g / n 20t.

A probe warehouse of reinforced concrete structures is located in the zone of the mounting crane.

Installation of structures is carried out using a tower crane.

Before lifting and moving prefabricated elements to the installation zone, it is necessary:

-Purry elements of shaking, snow, nondes, and metal parts - from rust;

- Name the axial risks and check the presence of elements based on elements;

- check the correctness and reliability of the lines.

Lifting, moving and lowering elements should be performed smoothly, without jerks, swinging and rotation. Prefabricated elements must be installed in a design position with appropriate reconciliation and design of design fixtures in nodes.

Release structures from the lines can only after their fixation.

Installation of the designs of each overlying floor (tier) of a residential building should be made after the design fixing of all mounting elements and achieve by concrete (solution) of deployed joints of the carrying structures of the strength specified in the PPR.

In cases where permanent ties do not ensure the stability of structures during their assembly, it is necessary to apply temporary mounting links. The design and number of connections, as well as the order of their installation and removal, must be specified in the PPR.

Designs should be configured. Works on the next tier should be started only after the design consolidation of all the designs of the underlying tier.

The limit deviations from the combination of landmarks during the installation of prefabricated elements, as well as the deviations of the completed installation structures from the project position should not exceed the values \u200b\u200bgiven in Table 12. SP 70.13330-2012.

Brickwork

Brick laying of walls is performed in accordance with the project and requirements of the joint venture 70.13330-2012.

Brick delivery is carried out onboard vehicles in pallets.

The supply of bricks and a solution to the place of production of work is made by a tower crane.

It is not allowed to weaken the brick masonry by holes, furrows, niches, assembly openings not provided by the project.

The thickness of the horizontal seams of masonry from bricks and stones of the correct shape should be 12 mm, vertical seams - 10 mm.

When performing a masonry bursting with a vertical finish in the layer seams, the mesh (reinforcement) from the longitudinal rods with a diameter of no more than 6 mm, from transverse rods - not more than 3 mm with a distance of up to 1.5 m in laying height, as well as in each overlap level .

The number of longitudinal rods of reinforcement is taken at the rate of one rod for every 12 cm wall thickness, but not less than two with a wall thickness 12 cm.

The construction of the stone designs of the subsequent floor is allowed only after laying the bearing structures of the elevated floors, the walls of the walls and the insoluction of the seams between the slabs of overlaps.

The limiting height of the construction of free-standing stone walls (without laying overlaps or coatings) should not exceed the values \u200b\u200bspecified in Table.28. SP 70.13330-2012. If you need to build free-standing walls of greater height, temporary mounts should be applied.

The height of the stone unarmed partitions, not liberated by overlaps or temporary mounts, should not exceed 1.5 m for partitions with a thickness of 9 cm, made of stones and bricks on a rib with a thickness of 88 mm, and 1.8 m - for partitions with a thickness of 12 cm, made from Brick.

All mortgage reinforced concrete elements (eaves, belts, balconies, etc.) must be provided by temporary fasteners to pinch them by the overlying masonry. The time for removal of temporary fasteners must be observed according to work drawings.

Given that the seismicity of this area is 7 points when laying from bricks, it is necessary to comply with the following requirements:

The laying of stone structures should be produced on the thickness of the structure in each row;

The masonry of the walls should be performed using a single-row (chain) dressing;

Horizontal, vertical, transverse and longitudinal laying seams should be filled with a solution completely with a trimming solution on the outer sides of the masonry;

Temporary (mounting) breaks in the erected masonry should be edged only with a slanting fine and places outside the wall reinforcement of the walls.

It is not allowed to use bricks with a large content of salts protruding on their surfaces.

The surface of the brick before laying must be cleaned from dust and dirt:

For masonry on ordinary solutions - water jet;

For masonry on polymer cement solutions - with the help of brushes or compressed air.

Under the negative temperatures of the outer air, the masonry should be made on solums with contamination additives. At the same time, the following requirements must be followed:

Before the start of the masonry work, the optimal relationship between the preliminary moistening of the wall material and the water content of the mortar mixture should be determined;

Conventional solutions must be used with a high water-holding capacity (water supply no more than 2%).

Vertical of the faces and corners of brick and stones, the horizontal of its series must be checked along the completion of the masonry (after 0.5-0.6 m) with the elimination of detected deviations within the tier.

After the end of the masonry of each floor, the horizontal test should be carried out and from the top of the masonry label is unlucky from the intermediate checks of its horizontal rows.

Welding work

In the production of welding work, it is necessary to comply with the requirements of SNiP 12-04-2002, "Rules of fire regime in the Russian Federation", GOST 10922-90, GOST 14098-85.

The dimensions of the structural elements of welded joints of the rod fittings (rods between themselves and with elements of the mortgage products) and the limit deviations of the sizes of the joints must correspond to the specified in GOST 14098-85.

To perform mounting compounds of reinforcement steel of different classes, methods for welding and welding materials specified in Table 38 and 39 SP 70.13330-2012 should be applied.

Before assembling structures, it is necessary to establish compliance with the drawings of the CZH classes of the rod fittings, the stamps of the steel of flat mortgage products and connecting parts, and before welding - also sizes and accuracy of interconnecting elements. The accuracy of the assembly of the release of reinforcement rods must comply with the requirements of GOST 10922-90 and GOST 14098-85.

The length of the release of reinforcement rods from concrete construct must be at least 150 mM with regulated gaps regulated by regulatory documents and at least 100 mm when using insert.

Elements of precast concrete structures should be collected using devices and fixtures that fix their design position. Designs that have mortgage products of support should be additionally assembled on patches using the same welding materials as the main seams. The tapes should be placed in places of the subsequent imposition of welds.

When assembling structures, the cropping of the ends of the rods or the preparation of their electrical arc edges is not allowed.

After assembling under the welding, the inconsistency of the reinforced reinforcement rods, the fractures of their axes, offset and deviations of the sizes of welded items must comply with the requirements of GOST 10922-90. Rod bend to ensure their alignment is allowed to be heated to a temperature of 600-800 ° C.

The welding of structural elements should be performed in a securely fixed project position. It is forbidden to weld the release of reinforcement rods held by the crane.

After the welding is completed, the welded compound must be cleaned from slag and metal splashes.

Completed welding in front of concreting should issue acts of acceptance of a batch of fittings for external inspection.

The design of welded joints of the rod fittings, their types and methods of execution depending on the operating conditions, class and brands of the welded steel, diameter and spatial position during welding must comply with the requirements of GOST 14098-85.

The tack of arc welding in cruciform connections of the working reinforcement rods according to GOST 14098-85 is prohibited at negative temperatures.

On the surface of the rods of the working fittings, there are no arc welding burns.

In the joints of the reinforced concrete elements, the installed closed clamps (transverse rods) should be fixed, as a rule, knitted wire. Arm welding in places intersection of the rods of clamps with a longitudinal (working) reinforcement is allowed for some staries provided for by GOST 14098-85.

To perform manual or mechanized welding at a negative ambient temperature to minus 30 ° C, it is necessary:

Increase the welding current by 1% with a decrease in air temperature for every 3 ° C (from 0 ° C);

Producing pre-heated by gas flame of reinforcement rods up to 200-250 ° C for a length of 90-150 mm from the joint; Heated rods should be carried out after fixing inventory forms, steel brackets or round linings without disassembly of conductors used to temporarily fix the mounted structures;

Reduce the cooling rate by the welding rods made by baths by winding them asbestos; If there are inventory forming elements, you should shoot the latter after cooling the welded compound up to 100 ° C and below.

Manual welding of structures is allowed to perform without heating at ambient temperature shown in Table. SNiP 3.03.01-87.

The acceptance control of the welded joint joints of the reinforcement should provide for an external inspection and a set of tests carried out in accordance with GOST 10922-90 and GOST 23858-79.

The volume of the welded joints of the armature releases is set by the same standards. Concreting construction until the results of the quality assessment of welded connections are not allowed.

The cabinet allowed to correct defects should be produced by electrodes with a diameter of 4 mm after stripping the place of defect with an abrasive tool and a preheating of the joint to 200-250 ° C.

Welded shock connections of reinforcement, not satisfying the requirements of GOST 10922-90 or GOST 23858-79, must be cut. The intermediate insert with a length of at least 80 mm with subsequent ultrasonic control of two welded joints should be taken to the scene of the cut joint.

Roofing

Roofing work performed in accordance with the instructions
SP 17.13330.2011 "Roofs" and SP 71.13330-2012 "Insulating and finishing coatings", with compilation of PPR or using typical technological cards tied to local conditions and on instructions in the project drawings.

Works are carried out by seizures.

For the production of roofing work around the perimeter of the roof, it is necessary to establish a temporary limit fencing. Works on the roof coating device are performed only in the presence of outfits on working with increased danger.

Workers engaged in insulating and roofing works are provided by appropriate clothing, shoes and personal protective equipment. Roofers must have safety belts.

Place on the roof materials are allowed only in places stipulated by the project manufacturing project, with the adoption of measures against their fall, including from the impact of wind. During the interruption, technological devices, tools and materials must be fixed or removed from the roof.

The supply of roofing materials is provided by the help of load-lifting mechanisms provided for the production of the overhead cycle. Roofing work is performed using small mechanization, manual power tools and fixtures.

The roof areas on which roofing works are provided are provided by fire inventory and first-aid kits.

The device of each next roof element is performed only after checking the quality of the previous layer.

Vaporizolation is performed by a rolled rolled material dry, then plates of the mineral wool insulation are stacked.

Roofing PVC membrane canvas are welded with automatic welding using hot air. To the base of the membrane is attached using special dowels.

In the production of roofing works, it is envisaged to fulfill the requirements of labor protection in accordance with SNiP 12-04-2002, SP 12-135-2003.

In the production of roofing works, the input control of the applicants of the building materials are drawn up acts for hidden work, the protocols of laboratory tests of the applied materials.

Finishing work

Finishing works are manufactured after the construction, installation and special work. Before the start of work, the prepared surfaces are accepted on the act.

Finishing works are carried out on working drawings, according to the project manufacturing project or technological maps, taking into account the instructions
SP 71.13330-2012 "Insulating and finishing coatings",
MDS 12-30.2006 "Methodical recommendations on standards, rules and receptions of completed finishing works" and instructions for use.

Preparation of materials and delivery of them to the construction site is carried out centrally, vehicles.

The storage of materials and structures is carried out in accordance with the indications of standards, technical conditions for materials and structures. Storage of finishing materials and structures is made in closed heated warehouses.

Materials are applied to the placement site with the help of lifts and manually.

Finishing works are performed by the captures in a flow-dissected method with a rhythmic transition of the working complex brigade from one capture to another.

Workplaces are equipped, if necessary, inventory submits, stepladers, testers, with the installation of them at the floors of the building.

Brigades are equipped with relevant machines and mechanisms, sets of tools, inventors and fixtures.

Before the start of finishing work, the following works must be made:

Protection of the premises of atmospheric precipitation is performed;

The heat outline is organized, which provides indoor temperature not lower than 10 ºС and air humidity not more than 60%. For the heating of buildings, air heaters are used thermal guns or factory production calorificates.

Finishing of wall surfaces and ceilings

Plastering work is carried out by a mechanized method using plastering stations and manual plastering machines, painting works - using painting stations.

For plaster works, solutions (mixtures) are used, the composition of which is installed by the project and the manufacturer. In the shower, cement and cement-limestone solutions are used, for concrete walls - cement mortar (mixtures).

For the preparation of the solution to the place of installation on the construction site, a mobile plastering station is used. The solution is prepared and transported through pipelines and applied to the surface of nozzles.

In the production of internal plaster works, the following construction processes are sequentially performed.

When plastering internal brick walls:

Preparation of surfaces - Cleaning, Firmboard;

Wearing surfaces and installation of beacons (with high-quality plaster);

Applying the spray layers with a mechanized manner;

Leveling of layers outlines;

Pulling the thrust and cutting of the corners.

When plastering concrete surfaces:

Primer concrete surface;

Preparation of a liquid solution;

Applying the solution and putting it on the surface with a mechanized manner;

Finish finish of surfaces.

Technical requirements for the quality of work should be respected in accordance with Table 10 SNiP 3.04.01-87.

The quality control of plaster works is performed by the measuring method and visual inspection with registration in the general journal of work.

Coloring surfaces

In accordance with the project, the use of simple and improved painting of premises is envisaged. Category Coloring is established by the project.

The complex of painting works includes:

- preparation of paint compositions;

- preparation and processing of surfaces under the color;

- Color.

Painting formulations are prepared mainly centrally and entered the object in the factory container. Work is carried out using painting stations, on which painting formulations are brought to complete readiness to use.

Before coloring water compositions, the surface of plaster and concrete is cleaned and divened with a manual tool.

Shpening (under the improved color) is made by the spray gun.

The composition applied to the surface is resurrected by a spatula with a collection of residual putty mass in inventory boxes.

Grinding the shapuckled surface is carried out by grinding paper.

Coloring is made by the sprayer or roller.

Technical requirements for quality of work should be observed in accordance with Table 11 SP 71.13330-2012.

The quality control of painting works is performed by the measuring method and visual inspection with registration in the general journal of work.

Facing with ceramic tiles

Facing the inner walls with ceramic tiles is produced at a height of 2.1 m in the "wet" rooms.

The base for lining should be plastered without applying the stacker layer.

Solutions for facing the need for up to 3 m 3 in shift are prepared on the spot from ready-made dry mixtures. For greater need, solutions are delivered to the object from the manufacturer.

Works on the cladding of walls are performed according to the beacons aligned with the rail, as well as in terms of the level in the horizontal direction and on a plunder - vertical.

The thickness of the layer from the solution should be in the range of 0.7-1.5 cm, and the thickness of the seams between the tiles is not more than 0.3 cm. The same seam width is provided by inventory brackets that are laid between tiles in the seams.

Before laying, the tiles are immersed in water for 15-20 minutes. For better clutch with mortar.

The first row of tiles are based on the rail installed on the net floor. For laying the second row in the corners of the room, they put extreme tiles, check them on vertically along the upper beacon and lower row. The tiles are set, going from one corner to another along the cord-moor, strictly observing the vertical of the seams. In the same order, the tiles of the rest of the rows are placed.

After a day, the seams between the tiles are filled with a special grout solution (a mixture for grouting).

The finished surface is washed with water or wipes wet sponge.

Specifications for work quality must be respected in accordance with the SP Table 71.13330-2012.

Quality quality control is performed by the measuring method and visually with registration in the general journal of work.

Device floors

Works on the flooring are made after construction, assembly and special work, when performing a destruction or damage to the floor.

When developing projects for the production of works and technological maps, indications of the joint venture 29.13330.2011 "Floors" and MDS 31-11.2007 "Floor Device" should be taken into account.

The floors made of concrete and cement-sandy concrete base are arranged in the following sequence. The base is diverted and, if necessary, dried up, with the help of levels, the bearer railings are installed, the coating is satisfied with strips and length in the entire room. Work starts from the angle, the bands are filled through one prepared solution. The mixture is spacing, seal with vibrations and align with metal gladlicts. After grapping the solution (after a day) and the removal of the rivers, the missed bands are also filled with a solution.

Works on the device of floors from ceramic tiles are performed after laying a concrete underlying layer or device of a monolithic reinforced concrete plate. Before the start of the production of work, the basis is prepared - it is leveling, cliffs are closed, the bulges are cut down, dust and garbage are removed. To ensure the horizontal of the floor, lighthouses and stamps are exhibited, denoting a given level of pure floor. The prepared concrete surface is applied with a layer of bitumen mastic with a sprinkling of 5-15 mm with sand. In places of floor adjustment to walls and other structures protruding above the floor, waterproofing should continue to continue to a height of at least 300 mm on the floor coating level.

Rolls of waterpore are open with rollers-rollers (type CO-108A) and the flashes are laid at least 100 mm. To avoid local thickens of a roll carpet with a sticker, the panels of waterpores are pasted with mandatory disappearance of the joints in adjacent layers. Cold mastic is applied with a special machine (type SO-122A) or a fishing rod. The second layer of hydroisol is laid after the first drying of the first layer.

The coating of ceramic tiles is placed on a layer of cement-sandy solution or special mixtures with the help of the kitchen with separate strips of the inviprion along the long side of the room. The tiles are stacked by "seam in the seam", hailing with light blows of the hammer. With a large area of \u200b\u200bthe room, it is possible to use a packet method of laying tiles using templates and conductors.

After grapping and hardening the solution, the surface of the floor is wiping with a damp rag and is washed with water.

Outdoor coatings of linoleum are laid "dry" or on a glue, on a tie of cement mortar on clay sand. The solution is prepared on the construction site and is laid manually. Bearded rails are installed in front of the device on the level of level, the base is dying and dried if necessary. Screeds are arranged with stripes with a width of 2-4 m and length in the entire room. The bands are filled through one, their surface is loaded with vibration. After grapping the solution and removal of the rails, the missing bands are also filled with a solution, then the base is grouped and ground (if necessary).

The linoleum-sliced \u200b\u200bpanels are revealed and kept in such a position for at least a total of straightening and acquiring the room temperature at least +10 ºС. Laying rolls is made along the long side of the room.

A special spatula or brush glue is applied on the base for each cloth, leaving a 10 cm wide coated strip along the joint. Then the roll is rolled and pressed to the base with rollers. The joints of the cloth are connected by welding in place of electric specials. device ("Pilate", "soldering iron", etc.), special glue or welded in advance on the harvested area. After the linoleum stickers around the perimeter of the room attach plinths.

Porcelain tiles are stacked after the device of the connecting layer from the cement-sand solution (the thickness of the solution for the project). The solution is stacked manually, under beacons and vibrate.

Porcelain stoneware is laid immediately after the layer layer in the interlayer with the use of vibration or manually. The end of the processing of porcelain stamp must be prior to the start of the decaying of the solution. The width of the seams between the tiles should not exceed 3 mm. The seams are filled with this solution after 2-3 days after laying the coating.

Floor quality control is made in accordance with the instructions of the SP 71.13330-2012 Table. 16-25 and includes measuring and visual control methods with a reflection of the results in the general journal of work and the compilation of acts of acceptance of work performed.

Installation of internal engineering systems

Installation of internal cold water and sewage systems is made in accordance with the instructions of the joint venture 73.13330.2012 "Domestic sanitary and technical systems of buildings", typical technological cards approved by the Customer, as well as standards, technical conditions and instructions of equipment manufacturers.

Prior to the start of installation of domestic sanitary and electrical systems, basic construction works must be made, including:

Preparation of holes, furrows, niches and nests in the walls, partitions, overlaps and coatings required for laying pipelines and air ducts;

Installation in accordance with the working documentation of mortgage parts in building structures for fastening equipment, air ducts and pipelines;

Glazing window openings in outdoor fences, insulation of inputs and holes;

Application on the inner and outer walls of all premises of the auxiliary marks;

Ensuring the possibility of including power tools.

Installation of internal sanitary systems is carried out by a stream with a preliminary preparation and consolidating assembly of components and elements of pipelines in the procurement workshops of contracting organizations and plants.

Installation of risers and eyeliner is performed in the following sequence:

Packages with billets on storey risers are spread to installation places;

It is going to the riser and connects to the trunk pipeline;

The position of the riser is evaporated and constant fasteners are installed.

Mounting of reinforcement is carried out simultaneously with the installation of risers and eyeliner, and the water-based fittings are installed after installation of sanitary devices.

Construction structures Pipelines are attached to brackets, pendants, clamps, hooks.

When welding pipes, parts and nodes, the requirements of GOST 12.3.003-86 Nodes of sanitary systems should be tested for tightness at the place of their manufacture in accordance with
GOST 25136-82.

Hydraulic or pneumatic testing of pipelines with a hidden laying of pipelines should be made before they are closed with compiling an act of examining hidden work. The heating systems, heat supply, inner cold and hot water supply at the end of their installation should be washed with water until it is out of use without mechanical suspension. Washing systems of economic and drinking water supply is considered to be completed after water output satisfying the requirements of GOST R51232-98 "Drinking water",
Sanpin 2.1.4.1074-01 "Drinking water".

The organization and production of installation and commissioning of electrical devices is performed in accordance with
SP 76.13330-2012 "Electrical devices", GOST R.50669-94, standards, technical conditions, rules of electrical installations (Pue-2003) and departmental regulatory documents approved in the prescribed manner.

Prior to the production of work on the installation of electrical devices, an acceptance of the construction part of the object under the installation of electrical devices should be taken at the facility.

In the production of works by the electrical organization, the indications of the joint venture 112.13330-2012 "Fire safety of buildings and structures" and "the rules of fire regime in the Russian Federation" are carried out.

Commissioning works include a complex of work, including checking, setting up and testing electrical equipment in order to provide electrical parameters and modes specified by the project.

Installation of instruments and networking networks is carried out in accordance with the technical description of manufacturers and RD 78.145-93.

DEVICE OF INTERPLOY TRIPS AND PLATES

Works are manufactured by a flow method with a separation of the front of work on the sections and the capture.

A set of machines needed for road works is formed based on the volume of work on the project from among those available in a contracting organization. The contracting organization must have a production base to ensure road work with the necessary materials, semi-finished products and finished products. The device of intermediate storage sites is not provided.

The volume of road works includes:

Restoration and fixation of road tracks;

A fitting device of the soil under the trough of the roads;

Layout of the earth canvas;

Laying geotextile;

Laying 2-layer base from sand and rubble;

The coating device of the roads from 2 or 3-layers of asphalt concrete or monolithic reinforced concrete on the bitumen-sand layer (coating container sites);

Sorting stone device;

Equipment of the road with technical means of road traffic;

Improvement.

Prior to the start of the main work, a geodesic breakdown of structures, work on the design of design drainage, water-pipe tubes. Road construction is conducted with reduced places of relief, with the provision of open water reservoirs from the work area.

Development of recesses with a depth of 0.8 m is carried out using a bulldozer with moving to a mound up to 100 m.

The sealing of the base of the earth canvase is performed by self-propelled pneumatic cathips for 4-6 passages by one trailer with its coating by 0.3-0.5 m.

The final planning of aggregate is performed by the automotive drive.

Geotextile rolls are rapped parallel to the axis of the road with the allen. Work on the promotion of rolls starts from the lower side with respect to the flow of water.

Sand delivery and rubble are made by dump trucks. The distribution and resurrection of sand is carried out in layers by bulldozers, planning - automotive drivers and seal - pneumocatters. If necessary, water watering is produced.

The rubble base is placed in 2 layers by similar technology.

Asphalt concrete applied factory manufacture.

Laying the layers of the asphalt concrete coating is made immediately to the entire width of the roadway of the road with one or two asphalt paver, walking together in order to provide high-quality interface of adjacent bands.

To ensure the required leveling of the coating, the asphalt pavers must be equipped with an automatic tracking system.

Works on the asphalt coating device are carried out only at a positive air temperature. In rainy weather, work is not conducted.

Concreting container plates are made by strips.

The rail form (formwork) is mounted on a planned base, rolled out, then fittings are installed with a molding of a viscous one by each other, laying gaskets and pins of deformation seams.

Delivery of concrete mix from the manufacturer is made taking into account the length of its transportation to the place of concreting.

The concrete mixture is stacked with a distributor, taking into account the allowance for a seal. The seal and finishing of concrete into the coating is performed continuously concrete machine bundled with vibrators.

At the time of the production of works on roads under construction, temporary road signs are installed, which are then replaced with permanent.

At all stages of road works are drawn up acts on hidden work, a laboratory test of the quality of material and sealing of the soil is carried out with the refinement of the number of passes on one trace.

Household stones are installed on a concrete base and with stacking concrete from an outdoor side of a width of at least 100 mm. Filling seams between stones is made by cement mortar. Borf must repeat the design profile of the coating.

When developing PPR and testing the quality of work performed during the device of auto roads and travel, it is necessary to comply with the recommendations of the joint venture 78.13330-2012 "Automobile Roads".

The contractor in carrying out construction and installation work should be guided by the following regulatory documents:

SP 70.13330-2012 "Bearing and Fencing Constructions";

SNiP 3.04.01-87 "Insulating and finishing coatings";

PPB 10-382-00 "Rules of device and safe operation of lifting cranes";

SP 82.13330-2012 "Improvement of territories";

SNiP 3.05.04-85 * "External networks and water supply and sewage facilities";

Regulatory documents for the manufacture of materials and their use in construction;

SP 48.13330.2011 "Organization of construction";

SP 45.13330.2010 "Earth structures, grounds and foundations";

SP 60.13330.2010 "Heating, ventilation and air conditioning";

SP 14.13330.2011 "Construction in seismic areas";

SP 7.13130.2009 "Heating, ventilation and air conditioning. Fire requirements ";

SP 29.13330.2011 "Floors";

SP 112.13330-2012 "Fire safety of buildings and structures"

12 The need for construction in personnel, main building machines, mechanisms, vehicles, in fuel and flammable materials, as well as electrical energy, pair, water, temporary buildings and structures

The cost of resource requirements is performed according to MDS 12-46.2008 p.4.14.

When calculating water on the fire extinguishing of the object, it is necessary to indicate the place of water intake for fire extinguishing or the location of the fire tank. In addition, recommendations on the development at the PPR stage of the fire extinguishing scheme should be attended. This scheme should be placed at the entrance to the construction site next to the passport of the object.

13 Proposals for the quality control of the quality of construction and installation work, as well as supplied to the site and mounted equipment, structures and materials

Information about the construction quality management system is indicated, general requirements for quality control programs, quality control programs for construction contractors, construction quality assurance service.

14 Suggestions for organizing a geodesic and laboratory control

The geodesic support of construction and the organization of laboratory control is being developed.

15 The list of requirements to be taken into account in the working documentation developed on the basis of project documentation, in connection with the methods of building construction structures and installation techniques

This subsection is developed if there are particularly complex or unique installation methods that require the development of additional mortgage or other constructive solutions in the working documentation.

For traditional installation methods, it is sufficient to indicate that in this project there are traditional methods for the installation of building structures and equipment and additional requirements for the development of working documentation are not presented.

16 Justification of the need for housing and socio-domestic service personnel involved in construction

This section substantiates the need for housing and social support for personnel, provided that the construction is carried out using a watched method or community of workers.

If the construction will perform local contractors, it is indicated that the workers will live in the city (village) and socially domestic services will be carried out by existing infrastructure.

17 List of events and design solutions for the definition of technical means and methods of work that ensure the implementation of regulatory requirements for labor protection

There is a list of regulatory documents on labor protection, the goals and objectives for labor protection, hygienic requirements for the organization of construction and installation work, the organization of the workplace and further describes the protection of labor when performing the main types of work provided.

18 Environmental Protection Activities for Construction Period

The assessment of the possible negative impact of construction work on the environment (soil cover, plant and animal world, water, air (and appropriate monitoring measures for the state of the medium and the prevention of this impact are included.

19 Description of project decisions and measures for the protection of the facility during the construction period

Specific solutions for the protection of objects adopted in this project are indicated, as well as a list of actions in case of detecting suspicious subjects.

20 Justification of the adopted duration of the construction of the facility

It is indicated by the rationale for calculating the duration of construction, as well as the decision-making period of construction and the event to ensure the implementation of construction into a policy term (with the presence of a policy construction in the design task).

21 A list of measures for organizing monitoring for the state of buildings and structures located in close proximity to the object under construction

Includes the arrangement of a geodesic system of observations of precipitation and roll, periodic examination of foundations and supporting structures, buildings and structures and other events depending on local conditions.

During the construction of an unaccounted area or at the location of buildings on a regulatory distance from existing buildings, it is indicated that the project provides for the construction of buildings and structures on the regulatory disposal from existing buildings and structures, measures for the organization of monitoring is not required.

22 Building General Plan

On the construction general plan are applied:

- the place of all permanent and temporary buildings and structures;

- place placement of sites and warehouses of temporary storage of structures, products, materials and equipment;

- installation of stationary cranes and paths of moving heavy loading cranes;

-News;

- Software for the construction site with water, electricity, communication;

-Toless temporary networks indicating the points of their connection;

-Hest location of signs of fixing the center axes.

23 Calendar construction plan

The calendar construction plan is drawn up according to the following form:

Table (table number) - (table name)

Name of individual buildings, structures or types of work Full estimate cost, thousand rubles. Cost of construction and installation works, thousand rubles. The distribution of capital investments and volumes of construction and installation work on construction periods (quarters, years), thousand rubles.
H. H. H. H.

In the absence of estimated cost, the calendar plan can be represented by a linear schedule.

Project organization of construction

Construction of a multi-storey residential building with built-in rooms


Tom content:

Explanatory note

Applications:

Calendar construction plan

Statement of construction and installation work

Statement of the need for building materials and structures

Graphic materials:

common data

StroyPlan.


Explanatory note

Content:

General provisions

Characteristics of construction conditions

Organization of the construction site

Methods for the production of construction work

Basic constructive solutions

Geodesic support for construction

Labor protection measures

Environmental Conservation Conditions

Technical and economic indicators

Justification of the duration of construction

Justification of resource requirements

Schedule Needs in the main building machines

Justification of the number of working and needs in temporary buildings and facilities

The volume of work included in the estimate in accordance with the Solutions

1. General Provisions

1. General Provisions

Initial data for the development of PIC:

Work project.

Materials of engineering and geological research performed by "hydrochhxxxxxxxxxxxxxxxx."

POS was developed in accordance with the current all-Russian and departmental regulatory documents, the most important of which are:

- GOST R 21.1101-2009 Project documentation system for construction. Basic requirements for project and working documentation.

- SNiP 1.04.03-85 * The norms of the duration of construction and hurt in the construction of enterprises, buildings and structures.

- Snip 23-01-99 * Construction climatology (with a change in N 1).

- SP 48.13330.2011 Organization of construction. Actualized edition SNIP 12-01-2004.

- SP 126.13330.2012 Geodesic works in construction. Actualized edition Snip 3.01.03-84.

- GOST R 51248-99 Ways overhead rail crane.

- PB 10-383-00 rules of device and safe operation of lifting cranes *.
________________
* PB 10-383-00 do not work. Federal standards and regulations in the field of industrial safety are operating "The safety rules of hazardous production facilities on which lifting structures are used" approved by order of Rostechnadzor from 12.11.2013 N 533.

- Snip 12-03-2001 Labor safety in construction. Part 1. General requirements.

- Snip 12-04-2002 Labor safety in construction. Part 2. Building production.

- Decree of the Government of the Russian Federation of April 25, 2012 N 390 on fire regime.

- Sanpin 2.2.3.1384-03 "Hygienic requirements for organizing construction production and construction work."

- One hundred Nostroy 2.33.52-2011 Organization of construction production. Organization of the construction site. New construction.

- One hundred Nostroy 2.27.17-2011 Mastering the underground space. Laying underground engineering communications by the method of horizontal directional drilling.

- Estimated standards for compiling construction organization projects. Part I (2nd edition, supplemented).

- Estimated standards for compiling construction organization projects. Part II.

- Estimated standards for compiling construction organization projects. Part VI.

- MDS 12-46.2008 Methodical recommendations for the development and design of the project organization of the construction, project organization of work on demolition (dismantling), project production project.

2. The nature of construction and the conditions for its implementation

2.1. This project documentation provides for the construction of a multi-level residential building with built-in premises.

The projected object is located in the Pushkin administrative district of St. Petersburg, Pos. Shushary, ul.Hhhhhhhh, D.Hh, Lit.x, residential house NXX.

The plot planned for development is located in the area of \u200b\u200bpromising development on the intra-quarterly territory and belongs to the right of ownership of the construction company XXXXXXXXX.

From the north, the South and the West, the construction site is limited by the land of farmland, from the east, the site is limited by the existing construction site. The plot is free from development and green plantings and is characterized by flat relief.

In the territory of the construction site there are air lines of power lines, which will be cabled before the construction.

The construction area refers to the I territorial belt of II of the climatic area.

The location of the object within the city gives the opportunity to use urban roads and engineering communications for the period of construction.

Work on the construction of an object is envisaged to carry out the forces of the general contracting organization with the involvement of specialized subcontracting organizations.

A contracting organization is determined by the customer.

The construction organization should have the necessary production facilities, a sufficient number of machines and mechanisms, as well as qualified personnel.

2.2. Building materials, products and structures will be delivered to the object centralized by road from industrial enterprises and construction enterprises of the city of St. Petersburg and the Leningrad Region on the following transport scheme:

- Commodity concrete - concrete plant LLC "XXXXXXXXXXX".

- Crushed stone - from the warehouse of OJSC Lentechstrom by road to a distance of up to 10 km.

- Sand - from a warehouse LLC "Stroytrans" by road to a distance of 20 km.

Building garbage, under the contract with the specialization, is shifted outside the construction site by road to the city dump up to 20 km away.

(Volkhonskoye highway 118, KPO polygon)

2.3. Brief climatological reference.

The city of St. Petersburg is located on the coast of the Finnish Baltic Sea bay at the mouth of the Neva River and on the islands of her delta. At the adjacent lowland and its continuation along the bay, the nearest suburbs are located.

The territory of the city and its surroundings is under the influence of marine (atlantic) and continental air masses of moderate latitudes, frequent entry of arctic air and active cyclonic activity. As a result of the interaction of all climate-forming factors, a climate is formed close to the sea, with a moderately warm wet summer and rather long-temperedly cold winter. The average annual air temperature is 4.2 ° C, and the period with a continuous temperature is 222 days. On average, a year in St. Petersburg is clear and cloudless days - 31, cloudy - 172, foggy - 57, semi-convertible, with variable clouds - 105. The positive air temperature is set from April 3 to November 11, during which time (222 days) On average, 126 rainy days (excluding short-term rains). In the cold period (143) of the day on average, 61 days with repeated precipitation (snow, hail, frost). In total, precipitation falls relatively few: 650-700 mm per year.

2.4. Engineering and geological and hydrogeological conditions of the construction site are characterized by a complex lithological structure - multilayer-layered soils by vertical, deep liabilities of dense (reference) soil layers. Soils are presented as follows:

- From the surface - bulk soils: sandy plastic, brown, mixed with sands of different chickens, wet, with gravel and pebbles, with construction garbage (broken brick, glass). Power is 0.40-1.70 m;

- Lake-glacial sediments - Suglinka Light dusty turn plastic, brown, with sands of sands dust, wet and saturated with water, with rare gravel and pebbles, roar. Power is 0.80-3.60 m;

- Glacial sediments - sandy plastic, gray, with sands of dusty, saturated with water, with gravel and pebbles up to 5-10%. Power is 0.80-1.50 m;

- Suglinka lungs and heavy dusty turn plastic, gray, with sands of dusty, saturated with water, with gravel and pebbles up to 5%. Power is 5.30-8.70 m;

- Suglinki heavy dust semi-solid, bluish-gray, with sands of dusty, saturated with water, with gravel and pebbles up to 5%. Power is 1.50-3.50 m;

- Cambrian deposits - clay heavy and light dustless solid, stationed, blue, with thin layers of sands dusty, with sandstone wreckage. Power is 4.00-8.40 m;

- Clay heavy and light dustless solid, blue, with thin sandstone bauddes. Power is 1.60-7.00 m.

The regulatory depth of the seasonal freezing for bulk soils is 1.39 m, for lake-glacial loams of staineer, ferrics are 1.15 m.

According to the degree of frosty bunchiness, bulk soils relate to mid-frequency soils, the sands dusty dense belong to the stronger soils, the sands are large, medium density and the dense and sands of medium size, dense belongs to practically non-bunched soils.

The hydrogeological conditions of the section of work on the depth of drilling are characterized by the presence of groundwater, dedicated to modern bulk soils, to quaternary sediments: to lenses and sands of sands in lake-glacial and glacial lines and squeees.

During the period of exploration, groundwater is opened at the depths of 0.80-1.60 m. WATER PROVIDE. The levels opened in the drilling process can be attributed to the average annual.

The maximum multi-year amplitude of the oscillation of the groundwater level is 1.50-1.80 m.

In unfavorable periods of the year (period of rain and intensive snowstation), we can expect the appearance of water like "Ripper" in bulk soils at the marks of the day surface.

2.5. Residential house NXX is designed sectional type. It consists of fifteen sections. The plan has a complex configuration, with dimensions in A - K8 axes: 218 m; In the axes 1 - K2: 95 m. Designed building of a variable floor: 16-24 floors. The residential building is designed with the basement and technical floor.

The basement is intended for laying engineering networks. The basement also contains technical premises, including: water grooves, individual thermal items for residential premises, individual heat points for built-in premises, indoor cable entry, pumping stations.

On the first floor there are built-in premises, an intended project appointment - office, according to demands for non-residential premises (clause 4.10.17 SNiP 31-01-2003 residential complex buildings). From the second to twenty-third floors, residential apartments are located.

The technical floor is also provided for laying engineering networks. The height of the basement is 3 m; The height of the 1st floor is 4.8 m; The height of the standard floor is 2.85 m; The height of the technical floor is 2 m. Heights are indicated on the level of clean floor to the level of pure floor of the overlying floor.

The foundation of a residential building is accepted by boards-pile; The pile foundation is designed from round boronobiling piles with a diameter of 600 mm and a length of 15 m and precast concrete (clogged) piles of a square section of 350x350 with a length of 15 m. Piles are combined with a monolithic reinforced concrete frame with a height of 700 mm.

The outer walls of the basement monolithic thickness of 200 mm. Plate overlap the basement monolithic boiled thickness of 300 mm.

Also there is also an inlet waterproofing of the outer walls of the basement and the coating for the foundation plate.

Bearing construction of a bonding type building, i.e. All horizontal loads are perceived by the core of stiffness. The spatial rigidity of the building is ensured by the joint work of vertical supporting structures, combined with rigid disks of intermediate floors.

Internal bearing longitudinal and transverse walls of all floors are made of a monolithic reinforced concrete with a thickness of 200 mm. Interlated overlap and coating monolithic booming 200 mm thickness.

A self-supporting wall of aeco-concrete blocks "AEROC", a thickness of 200 mm, a density of 400 kg / m, an external insulation of mineral wool plates "Tehnofas", 150 mm thick, 180 kg / m thickness and a thickness of 10 mm thick are 180 kg / m. The first floor of the designed building is facing the decorative tile. Walls are based on overlap. The facing layer is attached to the pylons using anchor releases through 3 rows of masonry. Inspecially partitions Silicate 100 mm thick, 1600 kg / m density.

The building is served by built-in unseasonable stairs. The stairs are made of monolithic reinforced concrete sites and precast concrete marches manufactured by Metrobeton CJSC.

In each section of the building there is an installation of 3 elevators: with a carrying capacity of 400 kg - 2pcs. and 630 kg - 1 pc. Elevator shafts are made of precast concrete.

Overhead elements - from galvanized steel with polymer coating.

Coloring facades - weather-resistant facade paints.

Locked Networks: The network of economic - drinking water pipes is designed from PE100 SDR17 F315 pipes, inputs - HCHG Du 100 mm; Water supply of the projected home nxx seen and is carried out for:

- Sections 1, 2, 3 - two water supply inputs from HCHG Du 100 mm pipes from the network of economic and drinking water pipes with a diameter of 225 mm from PE100 SDR17 pipes.

- sections 4, 5, 6 - two water inputs from HCHG Du 100 mm;

- sections 6, 7, 8, 9 - two water inputs from pipes of HCHHH Du 100 mm;

- sections 10, 11, 12 - two plumbing inputs from pipes of HCHG Du 100 mm;

- Sections 13, 14, 15 - two plumbing inputs from HCHHH Du 100 mm pipes from the network of economic and drinking water pipes with a diameter of 315 mm from PE100 SDR17 pipes.

Hot water pipes are made of steel water and gas pipes.

Household sewage is designed from PP 250 SN8 type "PRAGMA". Releases from the house of HCHG 100 pipes.

Drainage is designed from polyethylene corrugated pipes of the company "Melikon Polan" with a diameter of 160 mm with perforation and hole protection with a geotextile material.

The maximum weight of the lifting load (element of the elevator shaft) is 4.1 tons.

3. Consolidated calendar construction plan

3.1. A consolidated calendar construction plan is based on a consolidated estimated calculation and timing of the construction of a multi-storey residential building, taking into account the built-in premises.

The length of construction of the designed building was determined according to SNiP 1.04.03-85 * Part II Chapter 3-5 p.19; 35 extrapolation method:

Calculation of the duration of the construction of a different-purpose residential building with built-in premises with 119941 M.extrapolation method (SNiP 1.04.03-85 * Part I, p.4, application ):

The duration of construction is determined on the basis of the duration of the 22-storey residential building and is 14 months, taking into account the device of the pile base, the duration increases for 4 months.

The duration of the pile base device is displayed on the calendar graph. Taking into account the maximum combination of work and the use of 2 cranes, the total duration of construction will be 33 months, including the preparatory period - 3 months (gasket outdoor networks).

The timing and sequence of the construction of the building and structures, as well as the volume of capital investments and construction and installation work, are given in the "Consolidated Calendar Plan of Construction".

A consolidated calendar plan is made without binding to a specific calendar month of start of work.

3.2. The volumes of major construction and installation work are defined by similar objects and are shown in Appendix N 1.

Based on the volume of work, the need for construction in structures and materials is determined and is given in Appendix N 2.

The volume of construction and installation work and the need for construction structures will be refined at the further stage of design.

4. Brief description of construction and installation work methods

4.1. The construction of the object is conducted in 2 periods.

The preparatory period includes the following work:

- creation of a geodetic center basis for construction;

- clearing construction site;

- installation of temporary fencing;

- the creation of a revolving warehouse economy;

- ensuring travel to the construction site and the organization for it movement of construction equipment;

- alignment of the necessary construction equipment;

- Connecting household premises of builders to existing engineering networks.

The main period is included in: work on the construction of the department of general (family) practices with fitted premises, laying engineering networks, the device of roads and platforms, landscaping of the territory.

4.2. Before the start of work, the customer should be broken and securely fixed by signs (referees) the supporting geodesic network, from which the general contracting organization performs work on the breakdown of the construction grid in accordance with the requirements of the project.

The accuracy of the center work, the method and procedure for constructing a geodetic basis to be carried out in accordance with the requirements of the joint venture 126.13330.2012 geodesic work in construction. Actualized edition Snip 3.01.03-84.

4.3. On construction, only inventory devices and devices, manufactured according to typical projects and drawings of design organizations, should be applied.

Ensuring fire safety is carried out in accordance with the requirements of the "Decision of the Government of the Russian Federation of April 25, 2012 N 390 on fire-fighting mode."

During the production and installation work, it is necessary to provide coverage of places of work, entrances and storage areas.

The lighting of the construction site is a projector from the lamps installed on metal masts.

Driving vehicles to the construction site is carried out by the 10th pass.

Temporary roads are coated with coated reinforced concrete road plates 3.0x1.75 m.

As a fence, the construction site provides for the use of an existing concrete fence and a temporary metal fence device. At entry into the construction site, information shields are installed in such a way that they are located face side towards the approaching transport.

When traveling to organize a platform for washing wheels of vehicles, traveling to the track, to eliminate cases of contamination by the ground part of the roadway and motor vehicles working on construction. It is recommended to use the installation of "Moidodyr-2" to clean the water of vehicles.

Materials are stored at open storage sites in compliance with safety requirements and SanPiN 2.2.3.1384-03.

Temporary buildings adopted inventory: mobile carriages-forms VD-2M. Household premises should be equipped in accordance with SanPine 2.2.3.1384-03. Sanitary and household premises are encouraged near the entrances to the construction site.

Household premises are equipped with internal water supply, sewage and electric heating. Temporary heat supply on the construction of an object is not envisaged.

The construction site should be equipped with the necessary safety signs and visual agitation.

A comprehensive mechanization of construction and installation work was adopted using the mechanisms in two shifts. Construction and installation works are conducted during 8 to 23 hours. Working with mechanisms producing noise (compressor, centrifugal pump, welding transformer) is carried out with 9 to 18 hours.

All construction workers are provided by benign drinking water that meets the requirements of the current sanitary rules and the norms set forth in Sanpin 2.2.3.1384-03. Drinking water is delivered in the bottle of motor vehicles.

The average amount of drinking water required for one worker is determined by 1.0-1.5 liters in winter; 3.0-3.5 liters in summer. The water temperature for drinking purposes should be no less than 8 ° C and not higher than 20 ° C.

Power supply on the object is provided in specially provided household premises. They created conditions for warming up and receiving cold and hot food.

4.4. Before starting the production of earthworks, it is necessary to call representatives of interested services and owners of engineering communications in order to determine the actual location of networks and coordination of work methods. In the presence of a number of active cables, earthworks are carried out under direct supervision and guidance of the ITR appointed by the order. When communications not specified in the project are found, earthworks are discontinued, and to call representatives of the customer and the designer.

In the production of earthworks, it is guided by the requirements of SNiP 3.02.01-87.

In the process of performing the work of the "zero cycle", it is necessary to organize a permanent technical supervision of the state of the soil and compliance with safety in the work of work.

Earthworks start only after the adoption of all measures that exclude damage to underground communications.

4.5. Earthworks on the object are recommended to perform the following machines and mechanisms:

- planning work - DZ-101 bulldozer; Because Kotlovan is envisaged open. It is necessary to check out for technology with a bias 1:12.

- the development of the soil - the Volvo type excavator with a bucket capacity of 1 m with further loading in the automotive industry and disbound of unnecessary soil up to 20 km;

- Poverty backpage and tranches - DZ-101 type bulldozer.

The backflow of the sinuses of the kittlers (trenche) is performed by the sand of the average size with a layer-by-layer seal of pneumatic glasses of the TP-1 type.

Before the start of the framework of the framework, perform the bottom of the bottom of the pit (trenches) and strengthen the bottom of the layer of rubble solid rocks with a thickness of 100 mm. Since the pit is assumed to be closed - to provide a descent device for workers.

Bring out the passage of the kittlers, trenches and the preparation of the base under the foundations only after the end and acceptance of work on the vertical layout, which ensures reliable fast flow of surface water.

4.6. When developing the soil and work of work in the pitchers and trenches, it is necessary to provide measures to prevent soil collapse. For this, based on the requirements of the construction standards and the rules, it is necessary in the PPR, taking into account the geological and hydrogeological conditions of the site and the load from construction vehicles and stored materials, to determine the steepness of the slopes of the excavation or specify the mounting project of the walls of the pit.

The device of recreation and trenches with the embezzlement of slopes 1: 0.67 (the depth is 2.8 m; soils - loam); In this project, the fastening of slopes is not required.

For the period of production of works, construction water production is envisaged to produce a method of open water reservoirs, with a device of drainage grooves around the perimeter of the kittlers, the device of ZUMPF and pumping water from ZUMPF pumps with a capacity of 20 m / hour of the type C-245, GNOM. The volume of water for the construction slide is 25 m / day.

4.7. All work on the foundations must be performed in accordance with the indications of SNiP 3.02.01-87.

In the device of foundations, it is necessary to use the recommendations of TSN 50-302-2004 "Design of buildings and structures in St. Petersburg".

For submission to the place of operation of the required materials, the mounting pneumocolex crane COP 35719-1-02 is used. Pumping and laying of a concrete mix is \u200b\u200bcarried out using a concrete pump a straotter. Delivery of concrete mix is \u200b\u200bcarried out by Mixers such as ABS-7D.

4.8. Work on the construction of the ground part of the department of doctors is envisaged to perform the tower cranes of the KB-473 type with an arrow 30 m and the KB-401 crane installed on the rail path with a length of 37.5 m, parallel to the designed sections.

Binding tower cranes is shown in the "Buildingplane" drawing. The danger zone during the operation of the tower crane was determined in accordance with SNiP 12-02-2001 Part I "Labor Safety in Construction" at the height of the designed building of 74 m and is 11 meters.

The placement of temporary buildings and structures is specified in place.

4.9. With the construction of monolithic reinforced concrete structures of the designed building, the construction of the construction organization provides for the consistent implementation of formwork, reinforcement and concrete work.

Stacking concrete in the design it is necessary to maintain with a bunker for concrete.

Delivery of concrete mix is \u200b\u200bcarried out from the concrete node using concrete rates. During the production of concrete work, it is necessary to conduct careful control over the technology of preparation of concrete mixture, its laying, selection and test of control samples of concrete, while the control samples should be kept and gaining strength under the same conditions as concrete stacked in the case.

Before concreting, the formwork surface must be cleaned from garbage, dirt, oils, snow and ice.

Concrete mixtures should be laid in concrete structures with horizontal layers of the same thickness without breaks, with a sequential direction of laying in one direction in all layers.

Laying of all subsequent layers of concrete mix is \u200b\u200ballowed until the sequence of concrete of the previous layer.

The top level of the concrete mix should be 50-70 mm below the top of the formwork shields.

The laid concrete is condensed with surface vibrators of the IV-91A type or depth IV-112 vibrators.

In concreting of monolithic floors, it is advisable to apply the inventory formwork for multiple turnover of type "Proplex" or "Alumasystem".

Reinforcement of structures is envisaged with pre-harvested grids and spatial frames.

All installation, reinforcement, formwork and concrete works should be performed in accordance with the indications of section 2 "concrete work" SNiP 3.03.01-87 "carrying and enclosing structures", inlet and coating waterproofing of the bottom and walls of the basement in accordance with the indications of SNiP 3.04. 03-85 "Protection of building structures and constructions from corrosion."

4.10. Roofing work must be carried out in accurately in accordance with working drawings, project manufacturing project, in compliance with the requirements of SNiP 3.04.01-87 "Insulating and finishing coatings", SNIP 12-03-2001, SNiP 12-04-2002 "Labor Safety in Construction" . Basic works on the roof device are performed after the monolithic reinforced concrete coating. The area of \u200b\u200bthe coating before the work began to smash the capture. The area of \u200b\u200bthe capture is advisable to take within the watershed.

Works lead subject to safety measures (temporary fencing of the work area, the use of safety belts, supplying overalls, shoes, etc.), which are additionally developed in the PPR.

4.11. Internal plastering and painting work in heated premises, for which it is for the beginning of work to mount constant heating systems, close the outer contour of the building. Finishing works are performed after accepting the surfaces of the walls and ceilings by the Commission with the participation of a subcontractor organization that performs these works.

Finishing works are envisaged to perform with inventory hinged and panel lumps and lobes at the place installed inside the building. The outer decoration can be performed with inventory metal tubular forests, or using AGP-24 auto leader.

Plaster works are performed using PRSC-1M plastering stations and manual plastering machines of the CO-112B or CO-86A.

To align the preparations for the floors and the device of monolithic clean flooring and platforms, the vibrores of the C810 brand should be applied.

Painting works are provided to perform with the use of PMS painting stations, painting aggregates of the brand 2600NA or 700N-1.

4.12. The device designs of engineering networks of water supply and sewage is performed by the TG-10 type pipelayer. All types of work on network laying are made in accordance with the requirements of SNiP 3.02.01-87, SNiP 3.05.04-85.

The installation of elements of heatplets is envisaged to perform a COP-type autocrantee 35719-1-02 in accordance with the requirements of SNiP 3.05.03-85.

Pipe materials: Plumbers - PE (polyethylene), sewage - VCHHHsh (inputs) and PP (polypropylene - pipes), thermal networks - steel.

4.13. The device of the earthen road sheet is carried out by sucking on autosmobiles with a subsequent layout of the DZ-42 type bulldozer, profiling of the DZ-143 type motor grader with a compaction of the Du-16G type pneumocole roller.

Coatings and bases made of asphalt concrete mixtures should be arranged in dry weather. Styling hot and cold mixtures should be produced in spring and summer at ambient temperature at least 5 ° C, in the fall - not lower than 10 ° C; Warm blends - at a temperature not lower than minus 10 ° C. It is allowed to perform work using asphalt concrete mixtures at an air temperature not lower than 0 ° C subject to the following requirements:

- the thickness of the arranged layer must be at least 4 cm;

- It is necessary to use asphalt concrete mixtures with surfactants or activated mineral powders;

- It should be arranged, as a rule, only the bottom layer of a two-layer asphalt concrete coating; If in the winter or spring, vehicles will be moved along this layer, it should be arranged from dense asphalt concrete mixtures;

- The upper layer is allowed to be armed only on the freshly fledged lower layer before its cooling (while maintaining the temperature of the lower layer at least 20 ° C).

Stacking asphalt mixtures should be carried out by the ds-126 asphalt paver. The temperature of asphalt concrete mixtures when laying in the structural layers of road clothing must comply with the requirements of GOST 9128-84 *. Sealing blends should be started immediately after their laying.
________________
* GOST 9128-84 does not work. GOST 9128-2009 is valid (the order of Rostechregulation from 22.04.2010 N 62-st). - Note database manufacturer.

4.14. Production of work in winter conditions.

In the preparation of the construction site and facilities under construction, special activities, as well as methods of transportation and storage of materials, semi-finished products and structures, must be provided for the production of work in winter conditions.

Earthworks are permitted to comply with the special project of the work of work in accordance with the indications of SNiP 3.02.01-87 "Earth structures, foundations and foundations". The development of frozen soil by a single-blood excavator without prior loosening is allowed with the thickness of the frozen layer to 0.25 m. When freezing to a large depth, the soil must be prepared in one of the following methods: the soil protection against frost, thawing the frozen soil, loosening the frozen soil.

The preparation method should be chosen and justified with the PPR, depending on the volume and conditions of work, the timing of their implementation and availability of equipment.

Concrete and reinforced concrete work in accordance with the indications of the section "Production of work at negative air temperatures" SNiP 3.03.01-87. When transporting a concrete mixture, it is necessary to take measures against its cooling on the way and during overloads, for which the container is insulated and warming up, and with large frost and snowfall, the concrete mixture is covered with tarpaulos. Places of loading and unloading of the concrete mix are protected from wind. Concreting monolithic structures is performed using concrete electrical heating. At the same time, the formwork of structures is insulated. On the construction site of concrete electric strokes are arranged. Concrete strength required to maintain further work is set in working drawings.

Insulating and finishing coatings should be performed in accordance with the indications of SNiP 3.04.01-87. Insulating and roofing works are allowed at ambient temperature to minus 30 ° C (production with hot mastic - at ambient air temperature not lower than minus 20 ° C, using water-based compounds without contamination additives - not lower than 5 ° C) . At the same time, the rolled roof is recommended to perform only one layer, and the remaining layers are performed in the warm season after the inspection and, if necessary, the repair of the first layer. Works lead subject to safety measures (temporary fencing of the work area, the use of safety belts, supplying overalls, shoes, etc.), which are additionally developed in the PPR.

Internal finishing works should be carried out at the positive ambient temperature and the surfaces of the surfaces are not lower than 10 ° C and air humidity not more than 60%. This temperature in the room must be maintained around the clock, not less than 2 days before the start and 12 days after the end of the work.

Work on the construction of an administrative and office building and engineering communications to perform in strict accordance with the rules of safety regulations set forth in SNiP 12-03-2001 Part 1 and SNiP 12-04-2002 Part II "Labor Safety in Construction".

The operation of tower and arrovar cranes should be carried out in accordance with the requirements of regulatory documents approved by the Gosgortkhnadzor of Russia.

Works of construction mechanisms: compressor, welding transformer, centrifugal pump, accompanied by sound effects, should be made from 9 to 18 hours according to Sanpine 2.2.3.1384-03.

5. Basic provisions for instrumental (geodesic) construction control

Production quality control should include input control of design and estimate documentation, products, materials and semi-finished products; Operational control of individual building processes or production operations and acceptance control of construction and installation work. At all stages of construction, in order to verify the effectiveness of previously performed production control, the inspection control of special services is selected or specially created for this purpose by commissions. According to the results of the production and inspection control of the quality of SMR, measures should be developed to eliminate the identified defects. When monitoring and accepting work, checked:

- compliance with the applied materials, products and designs with the requirements of the project, GOST, SNiP, TU

- compliance with the composition and volume of work performed by the project,

- the degree of compliance of controlled physical and mechanical, geometric and other indicators of the project requirements,

- timeliness and correctness of the design of production documentation,

- elimination of the shortcomings marked in journals of work input and supervision over the implementation of the SMR.

Geodesic instrumental control on the site is carried out in strict accordance with the requirements of SNiP 3.01.03-84 "Geodesic works in construction", GOST 22268-76 and GOST 24846-81. It is performed at:

- creation of a geodesic center base for construction (executed by the customer),

- locked work during the period of construction (executes the general contractor),

- monitoring the accuracy of the geometric parameters of the elevated object.

All geodesic work on construction should be carried out in accordance with projects for the production of geodesic works (PPGR). The points of the geodesic basis are fixed by constant and temporary signs. Permanent signs are laid for the entire period of construction and installation work, temporary - at the stages of work (earthworks, the structure of the foundations, underground and overhead part of the building).

The planned basis is created by methods of triangulation, trilaterations, polygonometry of the construction network and their combinations.

The altitude basis is created by geometric levelation.

To secure the points of the geodesic center base, the types of signs provided for SNiP 3.01.03-84 should be applied, specifying the depth of the attachment and design of the axes fixing signs into PPR.

During the construction, it is necessary to monitor the stability of the planned basis signs up to 2 times a year and the altitude base to 4 times a year.

The location of the signs are shown on the sheet of construction. After payment confirmation, the page will

Construction organization projects refer to project documentation (Stage "P"). The need to develop pos is dictated by the Decree of the Government of the Russian Federation No. 87 of February 16, 2008. On the composition of the partitions of project documentation and requirements for their content.

What is pos

The construction of the construction organization (PR) is a project documentation discharged under the A4 format consisting of textual and graphic parts. The composition of the construction organization's project was determined by clause 23 of the Decree of the Government of the Russian Federation No. 87 of February 16, 2008

The main task of the PR is the establishment of the basic parameters of future construction, such as:

  • determining the necessary capacity power supply construction;
  • definition necessary water requirements for the period of construction;
  • calculation and placement of temporary household buildings;
  • location temporary roads and platforms storage;
  • definition of directive Construction timing;
  • basic placement construction mechanisms;
  • definition stages and queues Construction.
Strogen plan for demolition of structures - sample

The composition of the village

In most cases, the staff of the Russian Federation No. 87 of February 16, 2008 are developed in accordance with the requirements of the Government of the Russian Federation No. 87 of February 16, 2008. The composition of the PIT can be expanded on the technical task (TK) coordinated with the Customer. Thus, the composition of the PC is divided into a regulatory, complemented and advanced.

The normative composition of the village

PIC in standard form consists of the following main elements:

Augmented composition of the village

The staff in the advanced form consists of the following main elements:

  • explanatory note indicating the main sections and calculations;
  • construction plan for the main period of construction;
  • incision for the building and cranes;
  • calendar construction schedule;
  • annexes to the project - permissive documentation (SRO, Certification).

Advanced composition of the village

The predicated form consists of the following main elements:

  • explanatory note indicating the main sections and calculations;
  • construction plan of the zero cycle of construction;
  • construction plan for the main period of construction;
  • incision for the building and cranes;
  • technological schemes for basic work processes;
  • drawings of temporary designs (if necessary);
  • calendar construction schedule;
  • annexes to the project - permissive documentation (SRO, Certification).
Crane cut (Advanced POS) - Sample

Development of the village

The development of the PIC is quite responsible work even for a small object. Despite the mandatory passage of the examination of project documentation (including POS), some companies do not provide due attention to this section. Competent development of the PIT is built at the following order:

  1. Buildingplane (construction master plan) - The most important part of the POS, decisive issues of the organization of the construction site and global security issues.
  2. Calculation of the duration of construction - (Section of the text part of the project) The task of the section is the correct calculation of the construction time of the object, and on this basis and such parameters, as the need for working personnel, temporary household facilities, construction machines and engineering.
  3. Other project sections - Full text part and calendar construction schedule (calendar construction plan).

STROYGENPLAN POS

The construction master plan in the composition of the PIT should solve the global issues of organizing the construction process, such as:

  • fence of the construction site and design boundaries;
  • the location and layout of household towns;
  • location on the plan of buildings and neighboring structures;
  • temporary roads, warehousing zones, wheel washers, gearbox, fire fights and electric cabinets, lighting masts, etc.;
  • binding the main lifting mechanisms (cranes) and optimize their parameters;
  • displays restrictions on the works of the cranes and the display of the main dangerous zones.
STROYGENPLAND POS - Sample

Despite the mandatory development Project production of works by cranes (PPRK) In the future - the main issues of safe work must be solved on the stage of the POS - the joint work of several tower cranes (the ratio of heights and departures of arrows), the correct binding and selection of the parameters of the cranes (height, departure, carrying capacity). As part of the pos, it is not allowed to bypass these issues with references to the PPC.

Later, at the stage of working documentation or before starting construction work at the facility - on the basis of decisions of the staff is developed STROYGENPLAN STAGE "P" .

Calendar construction schedule (or calendar construction plan) include a graphical display of a total duration of work, the duration of the implementation of individual works ( preparatory work, underground part, overhead part, finishing, etc.), as well as combined challenges in labor resources - working personnel. Properly designed Calendar plan It gives an informative visual representation - at what points of time and for the production of which work is needed a certain number of workers, IER and other personnel.


Calendar construction schedule - sample

The calendar schedule is obliged to consider all key points of construction. In the event of a resumption of the construction of an object after conservation, the stages of the works of previous years (before conservation) should be displayed on the calendar graph.

Examination and coordination of pos

All construction projects (pos) are examined by project documentation as part of the general project documentation. The choice of organization for the passage of the project documentation is carried out by the customer or the general designer of the object:

  • for objects of state importance (architectural monuments, cultural heritage, etc.) - state examination project documentation;
  • for other objects - non-state examination project documentation.

Who can develop pos

The development of the HAC is possible only by organizations that have access to the development of project documentation on capital construction facilities.

Although often design institutions have no own PIC engineers for high-quality project development, therefore they turn to third-party projectors (freelancers). You can read about the benefits and dangers of such development

The project of the construction of the PIC is a documentation where issues of the effective methods of organizing construction work in a particular situation on a specific facility are detailed. PIT is the main organizational document when erecting objects with industrial or non-productive purposes. The project contains measures for the use of modern technological and information funds, which make it possible to improve the quality of work, reduce the deadlines for the implementation of the entire project or its parts, reduce the cost of implementation.

The project is also developed when demolishing objects. When performing such operations, the PIT should ensure the safety of all operations, the correct disposal of waste and the absence of harm to the environment. Project organizations are engaged in the membership of the SRO with admission to certain types of work.

Composition of the construction organization

The composition of the organization's project and the content of its individual parts affects the complexity and specificity of objects, so the composition changes in accordance with the specific situation. The factors of influence include constructive solutions, the volume of planning works, the degree of uniqueness or use of typical solutions (as far as the object is unique), the need for the construction of auxiliary structures, the use of special devices, installations and devices, the specificity of the implementation of individual works. The composition of the POS influences how materials, equipment and various structures will be supplied to the construction site.

The construction project includes the following components:

  • explanatory note;
  • calendar plan for performing individual operations and all volume;
  • general plans for the preparatory and main stages of construction;
  • organizational and technological drawings, schemes and other graphic data;
  • information about the volume of construction, installation operations, additional work;
  • information on the necessary materials, pre-prepared structures, as well as used to solve the tasks of equipment;
  • plan of need for devices, machines, construction equipment and transport with specific information on dates;
  • information on the required frames for work.

Contents of the construction project

The most important parts of the project are the calendar plan for performing work and the master plan. If the remaining components may be present in a truncated form or not at all, then these are included in any pos, becoming its basis. All other statements and documents refer to the calendar schedule and the general plan, as for the rationale for their creation.

The calendar plan becomes a rational substantiation of the selected sequence. From the calendar plan of work it becomes clear why such an oddness is most effective, and in the organization of construction it is important. Clearly designate the timing of the execution of each stage of work.

The master plan describes the optimal accommodation on the entire construction site or its individual parts of the mechanisms for the lifting of goods, places for storing materials (some need special conditions), temporary roads for moving materials, mechanisms and various equipment, as well as other objects needed for construction . The master plan for the pos is different from a similar document for the project manufacturing a job with a more detailed answer to questions regarding ways to implement the tasks.

The explanatory note contains the details of the document, on the basis of which the project is started. This may be the decision of the developer, the implementation of the federal target program, a comprehensive program for the development of municipality and other documents. Here are the source data for the preparation of documentation, information on the functional purpose of the object, information about the need for utility services (gas, water, electricity, sewage). The correct project implementation allows not to spend unnecessary time to connect communications, not taken into account in the original plan. An explanatory note may contain other additional information, the volume of which depends on the complexity of the object being planned to build.

Source data for project development

The draft organization is carried out taking into account the data and documents that are present in the methodological recommendations. When creating a staff, the requirements of construction norms, a town-planning code, relevant federal laws apply. The provisions of the Decree of the Government of the Russian Federation dated 16.02.2008 N 87 are followed.

The development of the organizational project uses the initial data:

  • planning scheme and organization of land;
  • solutions for architecture and planning of cities;
  • constructive decisions;
  • project documentation for projected external networks of electricity, communication and other communications;
  • information about engineering and communication networks located in the execution zone and sources of water supply platform, electrical energy and necessary types of communication;
  • the statement of the number of major construction, installation and additional types of work;
  • a project of execution of operations for dismantling facilities (if construction is planned on the site of an existing object or simply demolition and dismantling of a production or non-production building).

The source data is needed to fill the relevant sections. Constructive solutions become the basis of the statements about the needs in certain structures for installation. To describe technological and organizational schemes, a significant amount of information is required, in the process of making the most efficient solutions, the initial data of several types are used in the process. Demolition work under the condition of new construction is not required, so the set of source data also does not imply the presence of all the items described without exception.

The basis for the development of the construction project project is the task of the customer with the technical conditions of implementation, which also applies to the number of source data.

The main objectives of the preparation of pos

The organization's draft is considered part of the construction of an object, in which the solution of all possible organizational issues arising during work is considered as much as possible. PRA concerns the entire volume of construction from the very beginning to commissioning.

The purpose of creating a project is to pass an object within the time limit. Effective organizational solutions make it possible to properly spend the allocated time, eliminate the probability of downtime due to problems with the supply of materials, a summary of technology, the impossibility of establishing in the event of the need for certain mechanisms and structures. The use of modern technologies takes into account the use of modern technologies, allowing to reduce the construction time and achieve quality required by standards and rules.

The project allows you to solve the following tasks:

  • the use of optimal methods of the organization to carry out construction in the minimum time;
    development of project power to the date established by the contract;
  • the use of modern technologies to comply with the requirements of construction standards and rules, ensure high quality;
  • timely supply of structures, materials, products on the object or its individual components (floors of a high-rise building, for example);
  • application of vehicles for quick installation of structures;
  • installation of technological equipment by large blocks, if there is an opportunity to reduce the duration of operations;
  • compliance with the security requirements and environmental protection in order not to exceed the standards from the technical regulation.

The project creation is maintained taking into account the peculiarities of natural and climatic conditions in the construction area. The implementation of many tasks at certain times of the year is simplified or complicated, the correct approach allows you to choose the optimal time to solve the tasks. Sometimes the possibility of delivering equipment and materials is influenced by seasonality, also play the role of territorial features. For the northern climatic zone, there are special security requirements related to increased risks. Also, special conditions are characterized by work in mountainous areas.

Requirements for design and content

The project includes textual and graphic components. Explanatory note contains only text, graphics can be applied in other sections as needed. In the graphic part there are schemes, drawings, plans and other documents in the form of graphics. The text component contains explanations, descriptions, information about the object, the reasons for making specific solutions, calculations, references to the technical documents and standards used during the design. There may also be diagrams, drawings, graphics and data in tabular form.

Conducting work in the conditions of cramped urban development requires a description of the causes of constraints and methods of construction in the designated situation. The safe performance of construction work in the danger zone requires the right organizational solutions in the form of limiting the zone of the movement of cranes, the arrangement of shelters and other structures to protect staff and other people, using screens.

The following data includes the construction section of the construction in the constrained building:

  • conditions of installation and specificity of work on the crane at a small distance from the pit;
  • the need to overlap streets at a certain time, restrictions on the movement of cars, changes in public transport routes;
  • organization of construction work near power lines to protect against damage to communication networks.

An important component of the organization of construction work is to satisfy the need for personnel and resources. This is clearly described by the number of necessary specialists and their employment period, a list of necessary materials and structures with optimal delivery data. The construction plan is a guarantee of the implementation of construction operations on time with appropriate quality.


2021.
Mamipizza.ru - Banks. Deposits and deposits. Money transfers. Loans and taxes. Money and state