DEPARTMENT OF CONSTRUCTION AND ARCHITECTURE

ORDER

ON THE FORM OF DOCUMENTS ATTACHED TO THE APPLICATION FOR THE PERMISSION TO COMMISSIONING THE FACILITY

(As amended by the orders of the Department of Construction and Architecture of the Administration of the Vladimir Region dated May 29, 2009 N 51-a, dated May 17, 2010 N 41-a, dated November 8, 2012 N 106/1)

In order to establish uniform requirements for the form of documents attached by the developer to the application for issuing a permit to put an object into operation in accordance with Article 55 of the Town Planning Code of the Russian Federation,

I order:

1. Approve the forms of documents:

1.1. On the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the requirements of design documentation in accordance with Appendix No. 1.

1.2. On the compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations in accordance with Appendix No. 2.

1.3. On the compliance of the constructed, reconstructed, repaired capital construction facility with the specifications in accordance with Appendix No. 3.

1.4. On the compliance of the parameters of the constructed, reconstructed linear facility with the requirements of design documentation in accordance with Appendix No. 4.

1.5. On the compliance of the constructed, reconstructed linear facility with the requirements of technical regulations in accordance with Appendix No. 5.

1.6. The act of acceptance into operation of the completed construction facility in accordance with Appendix No. 6.

(Clause 1.6 was introduced by order of the Department of Construction and Architecture of the Administration of the Vladimir Region dated May 29, 2009 N 51-a)

2. Department of architecture and urban planning:

Administration of the Vladimir region dated 05/17/2010 N 41-a)

2.1. To be guided by paragraph 1 of this order when checking the availability and correctness of the execution of documents attached by the developer to the application for issuing a permit to put objects into operation, if the issuance of permits to put an object into operation is attributed by the current legislation to the competence of the Department of Construction and Architecture of the regional administration.

2.2. Within ten days from the date of signing this order, send a copy of it to the local authorities that issue permits for putting objects into operation.

2.3. Post annexes to this order on the official website of the Department of Construction and Architecture of the regional administration on the Internet.

(Clause 2.3 was introduced by order of the Department of Construction and Architecture of the Administration of the Vladimir Region dated May 29, 2009 N 51-a)

3. Recommend local governments to be guided by paragraph 1 of this order when checking the availability and correctness of the documents attached by the developer to the application for issuing a permit to put objects into operation.

4. The control over the implementation of this order shall be assigned to the deputy director of the department, the chief architect of the region.

Department Director
construction and architecture
S.A.BOKOV

Appendix N 1. DOCUMENT on the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the requirements of design documentation

Appendix No. 1
to the order of the department
construction and architecture
administration of the Vladimir region
dated 13.03.2007 N 37

(as amended by the order of the Department of Construction and Architecture
administration of the Vladimir region dated 17.05.2010 N 41-a)

DOCUMENT on the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the requirements of project documentation

The location of the object _________________________________________________.

___________________________________________________________________________

Conclusion of the state expertise on project documentation****

N _____________________________ dated "____" _______________ _______ issued

___________________________________________________________________________
(name of the organization that conducted the state examination of the design
documentation)

List of buildings and structures included in the facility

Name of the building, structure

Type of work (new construction, reconstruction, overhaul)

Parameter name

unit of measurement

Built object

Total area of ​​the object

Number of floors above ground

Number of underground floors

Construction volume, incl. underground part

Height of floors above ground

Height of underground floors

Underground level

The height of the object, the mark of the highest point of the building, structure

Step of load-bearing walls, columns

building area

Other parameters

Types of engineering support of the object:

1. Engineering equipment interior

Name

Built object

Power supply

Water supply

Gas supply

Heating

Drainage

Ventilation

2. Outdoor networks

Length, m

According to the approved project documentation

Built object

Power supply

Water supply

Gas supply

Heat supply

Drainage

Structures and materials

Structural element

Structural solution and material

according to the approved project documentation

constructed object

Foundations

Exterior walls

Internal walls, partitions

Overlappings

Main power indicators of the object ***

Name of indicator

According to the approved project documentation

Built object

Number of sections

Number of apartments, incl.
1-room;
2-room;
3-room;
4 or more rooms

Number of workplaces

Performance

Capacity

Other indicators:

Energy efficiency indicators of the facility

Name of indicator

Standard value

actual value

specific value of consumption of energy resources, including:

Thermal energy, Gcal

Electrical energy, kW

Gas, cube m

Availability of metering devices, including:

Thermal energy, Gcal

Electrical energy, kW

Gas, cube m

Other indicators:

Parameters of the constructed, reconstructed, repaired facility
capital construction (strike out the unnecessary) __________________________
________________________________________________________________________
(name and location of the object *)

comply with the approved project documentation, including the requirements
energy efficiency and the requirements for equipping the facility with devices
accounting of used energy resources.

Placement of objects on the land plot corresponds to the scheme
planning organization of the land plot, approved in the
project documentation.

_______________________________________________ __________ ________________

"_____" _____________ 200__

M.p.
______________________________________ __________ ________________
(position of responsible representative (signature) (full name)
customer or developer)

"_____" ______ 20__

________________


approved project.

*** Power indicators of the object are indicated depending on its
destination.

**** In the event that, in accordance with the town planning
legislation, conducting a state examination of the design
documentation is not required, the words "not required" are entered in the column.

Annex N 2. DOCUMENT on the compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations

Appendix No. 2
to the order of the department
construction and architecture
administration of the Vladimir region
dated 13.03.2007 N 37


Name of the property * ________________________________________________________

___________________________________________________________________________

Builder ________________________________________________________________
(name of the organization, full name of the individual)

Customer __________________________________________________________________

Design documentation developed by ____________________________________________

___________________________________________________________________________
(name of design organization)

Construction was carried out:

General contractor of construction _______________________________________

___________________________________________________________________________

___________________________________________________________________________

___________________________________________________________________________

The main characteristics of the built, reconstructed,
renovated facility:

The total area of ​​the object, sq. m ______________________________________________

Construction volume, cub. m _____________, incl. underground part __________

Number of floors above ground ___________________, underground ________________

Height of floors overground _________________ m, underground _______________ m

Height of the object (mark of the roof ridge), m __________________________________

List of constructed (reconstructed) auxiliary facilities
destination ________________________________________________________________

___________________________________________________________________________
(garage, boiler room, TP, hydraulic fracturing, etc.)

Building area of ​​the building (buildings), sq. m __________________________________

Types of engineering support of the facility: _____________________________________

___________________________________________________________________________

water supply, sewerage, electricity supply, gas supply, heat supply,

___________________________________________________________________________
communication, centralized or individual

The constructed (reconstructed, repaired) capital facility

construction _____________________________________________________________
___________________________________________________________________________
(Object name *)

and its placement on the land plot meets the requirements of technical
regulations.


(position of the person carrying out the construction) (signature) (full name)

"___" ____________ 200__

________________


project.

Appendix N 3. DOCUMENT on the compliance of the constructed, reconstructed, repaired facility with the specifications

Appendix No. 3
to the order of the department
construction and architecture
administration of the Vladimir region
dated 13.03.2007 N 37

on the ________________________________________________________________________
(name of the type of engineering support: water supply,
power supply, etc.)

An object: ___________________________________________________________________

___________________________________________________________________________

Address of the object _____________________________________________________________

Builder (Customer) _____________________________________________________
(name of the organization, full name of the individual)

___________________________________________________________________________

Construction (reconstruction, overhaul) was carried out in

in accordance with the technical specifications N _____________ dated _________________,

issued by _________________________________________________________________

___________________________________________________________________________
(name of the organization that issued the specifications)

Design documentation developed by ____________________________________________

___________________________________________________________________________
(name of the person who completed the relevant section of the project)

___________________________________________________________________________

The work was carried out by ____________________________________________________________

___________________________________________________________________________
(name of the organization that performed the relevant type of work)

Conclusion:

As a result of the inspection of the object ______________________________________________

___________________________________________________________________________
(name of the object in accordance with the approved project)
it was established that the work was carried out in full in accordance with
specifications and allow for uninterrupted and safe
operation of the facility that meets current requirements

regulatory and technical documents, technical regulations.

___________________________________________________________________________
(name of engineering networks and structures)

accepted in the manner prescribed by law for balance, maintenance

___________________________________________________________________________
(name of the organization that accepted the networks for balance or maintenance)

________________________________________ __________ _____________________

operating organization) (signature) (full name)

"___" ________________ 200__

Annex N 4. DOCUMENT on the compliance of the parameters of the constructed, reconstructed linear facility with the requirements of design documentation

Appendix No. 4
to the order of the department
construction and architecture
administration of the Vladimir region
dated 13.03.2007 N 37

Name of the property * ________________________________________________________

___________________________________________________________________________

Address of the object _____________________________________________________________

Builder ________________________________________________________________
(name of the organization, full name of the individual)

Customer __________________________________________________________________

Design documentation developed by ____________________________________________

Conclusion of the state expertise on project documentation issued

___________________________________________________________________________
(name of the body of state expertise of project documentation)

___________________________ "___" ______________ ___ year N _______________

Construction was carried out ** ___________________________________________

on the basis of an agreement dated "___" _______________ 20_____ N _____________________


(strike out unnecessary)

The main parameters of the construction object

Parameter name

unit of measurement

According to the statement project documentation

Built object

Total length

Power (pressure, voltage, capacity, category, etc.)

For pipelines:

Laying method
(ground, aboveground, underground)

Pipe diameter

Gasket height
(with overhead method)

Depth
(for underground laying)

Material
Trumpets
Support (for above-ground laying)

For roads:

Road width within the right-of-way

Lane (track) width

Number of lanes

Estimated travel speed

Parameters of the constructed (reconstructed) linear object

___________________________________________________________________________
(Object name*)

___________________________________________________________________________
comply with the approved project documentation

Placement of a linear object on a land plot corresponds to the scheme
its placement, approved as part of the project documentation.

_______________________________________________ _________ _______________
(position of the person carrying out the construction) (signature) (full name)

_______________________________________________ _________ _______________
(position, responsible representative
Customer or developer) (signature) (full name)

"___" _____________ 200__

For roads:

Lane (track) width, m ___________, number of lanes _______

__________________________________________________________________________
(Object name *)

___________________________________ ___________ ____________________

construction)

"___" _____________ 200__

________________

* The name of the object is indicated in strict accordance with the approved
project.

** The name of the general contractor is indicated.

Appendix N 5. DOCUMENT on the compliance of the constructed, reconstructed linear facility with the requirements of technical regulations

Appendix No. 5
to the order of the department
construction and architecture
administration of the Vladimir region
dated 13.03.2007 N 37


Name of the property * ________________________________________________________

___________________________________________________________________________

Address of the object _____________________________________________________________

Builder ________________________________________________________________
(name of the organization, full name of the individual)

Customer __________________________________________________________________

Design documentation developed by ____________________________________________

___________________________________________________________________________

Construction was carried out (general construction contractor)

___________________________________________________________________________

Construction characteristic: new construction, renovation
(strike out unnecessary)

The main parameters of the constructed (reconstructed) object:

Total length, m ____________________________________________________

Power (pressure, voltage, capacity, category, etc.)__

___________________________________________________________________________

For pipelines:

Pipe diameter _____________________________________________________________

Laying method: above ground, above ground, underground (strike out unnecessary)

Laying height for above-ground method, m __________________, support material

Or pipe laying depth, m _______________

For roads:

The total width of the road within the boundaries of the right of way, m ___________________________

Lane (track) width, m _______, number of lanes ___________

Estimated speed, km/h _______________________________________________

Constructed (reconstructed) linear facility

___________________________________________________________________________
(Object name *)

___________________________________________________________________________
meets the requirements of technical regulations.

________________________________________ ___________ __________________
(position, full name of the person carrying out (signature) (full name)
construction)

"___" _______________ 200__

________________

* The name of the object is indicated in strict accordance with
approved project.

Appendix N 6. ACT of acceptance into operation of the completed construction facility

Appendix No. 6
to the order of the department
construction and architecture
administration of the Vladimir region
dated 13.03.2007 N 37

(as amended by the order of the Department of Construction and Architecture
administration of the Vladimir region dated 08.11.2012 N 106/1)

ACT of acceptance into operation of the completed construction facility


Compiled by "____" ____________ 20__

Composed of:

Representative(s) of the customer _______________________________________________
(full name, position)

___________________________________________________________________________

Representative(s) of the contractor ______________________________________________
(full name, position)

___________________________________________________________________________

Representative(s) of the subcontractor ___________________________________________
(full name, position)

___________________________________________________________________________

SET UP:

The contractor presented the commission for acceptance of the object: __________________

___________________________________________________________________________

Name of the property *

___________________________________________________________________________

located at: __________________________________________________

2. The construction was carried out in accordance with the permit for
construction N ________________, issued by "___" ________ 20__ _________

___________________________________________________________________________
(name of the authorized body that issued the building permit)

3. Construction was carried out by:

General Contractor _____________________________________________________
(name of organization, legal address)

___________________________________________________________________________
(information on the availability of SRO approval)

Subcontractors __________________________________________________
(name of organizations and their legal address)

___________________________________________________________________________

___________________________________________________________________________

4. Project documentation is developed by _____________________________________

___________________________________________________________________________
(name of organizations and their legal address, information on the availability

admission SRO)

4.1. The project documentation was approved** on the basis of a positive
conclusion of the state examination dated "__" ______ 20__ N ____________
state environmental expertise N ______ dated "___" ________ 20__

5. Construction and installation work was carried out on time:

beginning of work ________________
(month year)

completion of work ________________
(month year)

6. The object presented by the Contractor for delivery corresponds to the indicators
power and characteristics established in the project documentation, work
performed in accordance with the contract (agreement).

DECISION OF THE ACCEPTANCE COMMISSION:

Object submitted for acceptance:

___________________________________________________________________________
(name of the property*)

___________________________________________________________________________

___________________________________________________________________________
(object location)

made in accordance with the project, the requirements of technical regulations,
prepared for commissioning and accepted by the acceptance committee.

Signatures of commission members***:

__________ ____________________ _____________________
(position) (signature) (full name)

____________ ____________________ _____________________
(position) (signature) (full name)

Note:

* The name of the object is indicated in strict accordance with the approved
project.

** In the event that, in accordance with the town planning legislation
conducting state examination of project documentation,
state ecological expertise is not required, fit into the column
the words "not required".

*** Signatures of members of the commission - legal entities are certified by a seal.

An example of a completed act on the compliance of the constructed object with the requirements of technical regulations and project documentation

Hello, friends! In the last article, we considered the principle of drawing up an act of a completed construction object, and today we will talk about drawing up an act on the compliance of a constructed, reconstructed capital construction object with the requirements of technical regulations (norms and rules).

This document is required for issuing a commissioning permit. It is established in Part 3 of Art. 55 GRK RF.

Usually it is issued in the form of an act. Below is a sample of the completed version. You can also download the handicap of the act from the link an act of compliance with the parameters signed by the developer and the contractor.

Click on the picture to enlarge.

In addition to these two acts, it is still necessary to draw up an act on the compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation. Also, this document is needed for issuing a commissioning permit.

You may also be interested in:

Denis, if it's not difficult, explain by the asterisk at points 6 and 7?

1) Reading the explanation, I understand that these items are filled out for objects that do not require compliance certificates (project and technical regulations). Moreover, these points (6 and 7) are just in the act of conformity (which is not required).

2) If we fill out the entire act (it is required), then should we skip paragraphs 6 and 7?

3) If the project is not subject to state expertise, is an act of compliance with the project and those regulations required? And if required, then why do points 6 and 7?

Document confirming the conformity of the constructed object

For private houses built?

I figured it out myself, thanks for the site! A lot of useful information!

Greetings, Alexey. I'm glad you figured it out. Thanks for rating the site.

Question on the act on the conformity of the parameters of the constructed object. The object is an apartment building with engineering networks. In paragraph 3. Linear objects - all on-site networks are listed. What indicators fit, for example, power supply networks - the length of the network or the length of the cable? According to the project, the length of the network is 180 m.p., the length of the cables is 180*4=720 m.p. The cadastral engineer prescribes - the actual length of the network is 720 m.p. (it does not specify the length of the cable or the length of the network). I think there will be problems in obtaining permission to enter the building?

reconstructed an apartment in the Moscow Ring Road with the permission of OWN forces (there is no contractor). How then to draw up an act of a completed construction object and an act on the compliance of the reconstructed capital construction object with the requirements of technical regulations? Should I go to BTI, ZhEK or somewhere else?

The largest free information and reference system of online access to the complete collection of technical regulations of the Russian Federation. Huge database of technical standards ( more than 150 thousand documents) and a complete collection of national standards, authentic to the official database of the State Standard. GOSTRF.com is over 1 Terabyte free technical information for all Internet users. All electronic copies of the documents presented here can be distributed without any restrictions. Distribution of information from this site on any other resources is encouraged. Everyone has the right to unlimited access to these documents! Everyone has the right to know the requirements set out in these regulations!

on compliance of the constructed (reconstructed, repaired) capital construction facility with the requirements of technical regulations

"__" ____________ 200_

Customer _____________________________________ represented by ________________________

Acting on the basis ________________,

General contractor ____________________________ represented by ____________________________

Acting on the basis _______________,

with this certificate we confirm that the constructed (reconstructed, repaired) capital construction object __________________________

(select one) (name

object in accordance with the approved project documentation)

meets the requirements of technical regulations.

2. The construction was carried out according to the project ____________________________________

(name of the body that approved the project, date)

conclusion of the state examination of project documentation _________________

date of conclusion, adjustments)

3. Seasonal work (if the deadlines for their implementation are postponed) for landscaping, top coating of access roads to buildings, sidewalks, utility, playgrounds and sports grounds, as well as finishing elements of building facades must be completed and handed over to the owner in the manner prescribed by the norms within the following terms :

The act of compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the technical conditions on the territory of the Leninsky municipal district of the Moscow region

<19gt; Заполняется для каждого вида инженерных сетей отдельно.

<29gt; Заполняется в случае привлечения к строительству инженерных сетей и сооружений субподрядных организаций либо организаций, выполняющих "прямые" подрядные договоры с заказчиком (застройщиком, инвестором).

<39gt; Пункт заполняется по объектам, которые не подлежат государственному строительному надзору в соответствии с требованиями п. 1 ст. 54 Градостроительного кодекса РФ и в отношении которых не требуется оформление заключения о соответствии построенного, реконструированного, отремонтированного объекта капитального строительства требованиям технических регламентов (норм и правил) и проектной документации. В указанный перечень должны быть включены материалы лабораторных исследований, испытаний и экспертиз, выполняемых органами Госсанэпиднадзора Московской области.

<49gt; Заполняется для объектов бюджетного финансирования.

<59gt; Заполняется, если на объекте осуществлялся авторский надзор за строительством.

Certificate of compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations

Appendix No. 4 to the Administrative Regulations of the Administration of the Municipal Formation of the Serebryano-Prudsky Municipal District for the Provision of the Municipal Service "Issuance of a Permit for the Commissioning of a Capital Construction Object"

What else to download on the topic "Municipality9raquo;:

  • We will draw up a high-quality legal document
  • We specialize in all areas of law
  • Ask a question and get an answer within 10 minutes

Website-assistant for the preparation of various contracts.

Templates and forms. Everything is ready, from you - insert your data in the editor and print. If you have a template that you would like to post here, please use the feedback.

Document confirming the conformity of the constructed object sample

on the conformity of the parameters of the constructed (reconstructed,

"__" ____________ 200_

Acting on the basis ________________,

Customer ____________________________________ represented by _________________________

Acting on the basis ________________,

General contractor __________________________ represented by ______________________________

Acting on the basis ______________,

2. Construction (reconstruction, overhaul) of the capital construction object _______________________________________________________________

(name of the object in accordance with

approved project documentation)

located at: _________________________________________________

(indicate the full address of the object with the indication of the subject

Russian Federation, administrative region, etc. and building address)

was carried out under a project that has a positive opinion of the Moscow State Expertise dated "__" ____________________ 200_, No. _______________________, adjustment dated "__" ___________________ 200_ No. _________________________

3. Completed construction (reconstruction, overhaul) capital construction object has the following parameters:

1. Permission to put an object into operation is a document that certifies the completion of construction, reconstruction of a capital construction object in full in accordance with the construction permit, compliance of the constructed, reconstructed capital construction object with the urban planning plan of the land plot or, in the case of construction, reconstruction of a linear object the territory planning project and the territory surveying project, as well as project documentation.

2. To put the facility into operation, the developer shall apply to the federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body or an authorized organization exercising state management of the use of atomic energy and state management in the implementation of activities related to the development, manufacture, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Corporation for Space Activities "Roscosmos", which issued a construction permit, directly or through a multifunctional center with an application for issuing a permit to put the facility into operation.

3. To make a decision on issuing a permit to put an object into operation, the following documents are required:

1) title documents for the land plot;

2) the town-planning plan of the land plot or, in the case of construction or reconstruction of a linear facility, a territory planning project and a land surveying project;

3) building permit;

4) an act of acceptance of a capital construction object (in the case of construction, reconstruction on the basis of a contract);

5) a document confirming the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations and signed by the person carrying out the construction;

6) a document confirming the compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used, and signed by the person carrying out the construction (the person carrying out the construction and the developer or technical the customer in the case of construction, reconstruction on the basis of a contract, as well as the person exercising construction control, in the event of construction control on the basis of a contract), except for cases of construction, reconstruction of individual housing construction objects;

7) documents confirming the compliance of the constructed, reconstructed capital construction facility with the technical specifications and signed by representatives of organizations operating utility networks (if any);

8) a diagram showing the location of the constructed, reconstructed capital construction facility, the location of engineering and technical support networks within the boundaries of the land plot and the planning organization of the land plot and signed by the person carrying out the construction (the person carrying out the construction and the developer or technical customer in the case of construction, reconstruction on the basis of a contract), with the exception of cases of construction, reconstruction of a linear facility;

9) the conclusion of the state construction supervision body (in the event that state construction supervision is provided) on the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations and project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources , the conclusion of the federal state environmental supervision in the cases provided for by Part 7 of Article 54 of this Code;

10) a document confirming the conclusion of a contract of compulsory insurance of civil liability of the owner of a hazardous facility for causing harm as a result of an accident at a hazardous facility in accordance with the legislation of the Russian Federation on compulsory insurance of civil liability of the owner of a hazardous facility for causing harm as a result of an accident at a hazardous facility;

11) an act of acceptance of the work performed for the preservation of a cultural heritage object, approved by the relevant body for the protection of cultural heritage objects, determined by the Federal Law of June 25, 2002 N 73-FZ "On cultural heritage objects (monuments of history and culture) of the peoples of the Russian Federation", during restoration, conservation, repair of this object and its adaptation for modern use;

12) the technical plan of the capital construction facility, prepared in accordance with the Federal Law of July 24, 2007 N 221-FZ "On the State Cadastre of Real Estate";

3.1. The document and conclusion referred to in clauses 6 and 9 of part 3 of this article must contain information on the standard values ​​of the indicators included in the requirements for the energy efficiency of the capital construction object, and on the actual values ​​of such indicators determined in relation to the constructed, reconstructed capital construction object as a result of the studies, measurements, examinations, tests, as well as other information, on the basis of which the compliance of such an object with the requirements of energy efficiency and the requirements for its equipment with metering devices for the energy resources used is established. During the construction, reconstruction of an apartment building, the conclusion of the state construction supervision body must also contain information on the energy efficiency class of the apartment building, determined in accordance with the legislation on energy saving and on improving energy efficiency.

3.2. Documents (their copies or information contained in them) specified in paragraphs 1, 2, 3 and 9 of part 3 of this article are requested by the authorities specified in part 2 of this article, in state bodies, local governments and subordinate to state bodies or bodies local self-government organizations that have these documents at their disposal, if the developer has not submitted these documents on his own.

3.3. The documents referred to in clauses 1, 4, 5, 6, 7, 8, 12 and 13 of part 3 of this article shall be sent by the applicant independently if the said documents (their copies or information contained in them) are not at the disposal of public authorities, bodies local self-government or organizations subordinate to state bodies or local self-government bodies. If the documents specified in this part are at the disposal of state authorities, local governments or organizations subordinate to state bodies or local governments, such documents are requested by the body specified in part 2 of this article, in the bodies and organizations at the disposal of which the said documents, if the developer has not submitted these documents on his own.

4. The Government of the Russian Federation may establish, in addition to those provided for by Part 3 of this article, other documents necessary to obtain a permit to put an object into operation in order to obtain in full the information necessary for putting a capital construction object on state register.

4.1. To obtain a permit to put an object into operation, it is allowed to require only the documents specified in parts 3 and 4 of this article.

5. The body or authorized organization exercising state management of the use of atomic energy and state management in the implementation of activities related to the development, manufacture, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Space Corporation "Roscosmos", which issued a construction permit , within ten days from the date of receipt of an application for issuing a permit to put the object into operation, they are obliged to ensure the verification of the availability and correctness of the execution of the documents specified in Part 3 of this Article, inspection of the capital construction object and issue the applicant a permit to put the object into operation or refuse to issue permission, stating the reasons for refusal. During the inspection of the constructed, reconstructed capital construction object, the compliance of such an object with the requirements established in the building permit, urban planning plan of the land plot or, in the case of construction, reconstruction of a linear object, the territory planning project and the land surveying project, as well as the requirements of project documentation, including including the requirements of energy efficiency and the requirements for equipping a capital construction object with metering devices for the energy resources used, with the exception of cases of construction, reconstruction of an individual housing construction object. If during the construction, reconstruction of a capital construction object, state construction supervision is carried out, inspection of such an object by the body that issued the construction permit is not carried out.

6. The grounds for refusal to issue a permit to put the facility into operation are:

1) the absence of the documents specified in paragraph 3 of this article;

2) non-compliance of the capital construction object with the requirements of the town-planning plan of the land plot or, in the case of construction, reconstruction, overhaul of a linear object, with the requirements of the territory planning project and the territory surveying project;

3) non-compliance of the capital construction object with the requirements established in the building permit;

4) non-compliance of the parameters of the constructed, reconstructed capital construction facility with the design documentation. This basis does not apply to objects of individual housing construction.

6.1. Non-receipt (late receipt) of the documents requested in accordance with parts 3.2 and 3.3 of this article cannot be grounds for refusing to issue a permit to put the facility into operation.

Compliance of the constructed capital construction object

The grounds for refusal to issue a permit to put the object into operation, in addition to the grounds specified in part 6 of this article, is the developer's failure to comply with the requirements provided for in part 18 of article 51 of this Code. In this case, a permit to put the object into operation is issued only after it is transferred free of charge to the federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body or an authorized organization exercising state management of the use of atomic energy and state management in the implementation of activities related to the development , manufacturing, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Corporation for Space Activities Roscosmos, which issued a construction permit, information about the area, height and number of floors of the planned capital construction facility, about engineering and technical support networks, one a copy of a copy of the results of engineering surveys and one copy of each of the sections of the design documentation provided for in paragraphs 2, 8 - 10 and 11.1 of part 12 of Article 48 of this Code, or one copy of the fii schemes of the planning organization of the land plot with the designation of the location of the object of individual housing construction.

8. Refusal to issue a permit to put an object into operation may be challenged in court.

9. A permit to commission a facility (with the exception of a linear facility) is issued to the developer if the federal executive body, the executive body of the constituent entity of the Russian Federation, the local self-government body or an authorized organization exercising state management of the use of atomic energy and state management carrying out activities related to the development, manufacture, disposal of nuclear weapons and nuclear power plants for military purposes, or the State Corporation for Space Activities "Roscosmos", which issued a construction permit, was transferred free of charge a copy of the diagram showing the location of the constructed, reconstructed capital construction facility, the location of networks engineering and technical support within the boundaries of the land plot and the planning organization of the land plot, in order to place such a copy in the information system for providing urban planning ness.

10. Permission to put the facility into operation is the basis for state registration of the constructed capital construction facility, making changes to the state accounting documents of the reconstructed capital construction facility.

10.1. A mandatory annex to the permission to put the object into operation is the technical plan of the capital construction object submitted by the applicant, prepared in accordance with the Federal Law of July 24, 2007 N 221-ФЗ "On the State Cadastre of Real Estate".

11. The permit to put the object into operation must contain information about the capital construction object in the amount necessary for its state cadastral registration. The composition of such information must comply with the requirements established in accordance with the Federal Law of July 24, 2007 N 221-FZ "On the State Real Estate Cadastre" for the composition of information in the graphic and text parts of the technical plan.

11.1. After the completion of the construction of the capital construction object, the person carrying out the construction is obliged to transfer to the developer of such an object the results of engineering surveys, project documentation, certificates of examination of works, structures, sections of engineering and technical support networks of the capital construction object, other documentation necessary for the operation of such an object.

11.2. When carrying out work on the preservation of a cultural heritage object, a permit for the commissioning of such an object is issued taking into account the specifics established by the legislation of the Russian Federation on the protection of cultural heritage objects.

(Part 11.2 was introduced by Federal Law No. 315-FZ of October 22, 2014)

12. The form of permission to put an object into operation is established by the federal executive body authorized by the Government of the Russian Federation.

13. Within three days from the date of issuance of a permit to put an object into operation, the body that issued such a permit sends a copy of such a permit to the federal executive body authorized to exercise state construction supervision, if a permit has been issued for the commissioning of capital facilities. construction, specified in paragraph 5.1 of Article 6 of this Code, or to the executive authority of the constituent entity of the Russian Federation authorized to exercise state construction supervision, if a permit has been issued for the commissioning of other capital construction facilities.

document confirming the conformity of the constructed object sample

Appendix N 5 to the Administrative Regulations for the provision of municipal services "Preparation and issuance of permits for the commissioning of capital construction facilities by the administration of the Pavlovo-Posadsky municipal district of the Moscow region"

DOCUMENT ON COMPLIANCE OF THE CONSTRUCTED, RECONSTRUCTED CAPITAL CONSTRUCTION FACILITY WITH THE TECHNICAL CONDITIONS Organizations operating engineering and technical support networks confirm that the facility completed by construction and prepared for commissioning _____________________________________________ (name of the construction object ________________________________________________________________________________, (reconstruction, overhaul) in accordance with the design documentation) located at: _________________________________________________, (name of the municipal district; settlement or urban district, street, avenue, lane, etc.) complies with the technical conditions for connecting the facility to engineering and technical support networks ______________________________________________ (indicate the name of the engineering networks security, connection attached to the object _________________________________________________________________ of capital construction) Representatives of organizations operating utility networks: Heat supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature decoding) M.P. Hot water supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature) Cold water supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature) M.P. Wastewater reception (sewerage) _________________________________________________________________________________ (position) (name of organization) (signature) (signature transcript) M.P. Power supply _________________________________________________________________________________ (position) (name of organization) (signature) (signature transcript) M.P. Other networks ___________________________________________________________________________ (position) (name of organization) (signature) (signature transcript)

Good afternoon friends! We discussed notifications in previous articles. But here is the result of all, about the end, what is?

Of course, in the end, we all want to receive from the GOS bodies a conclusion on the compliance of the constructed, reconstructed capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices used energy resources.

Here is such a long name for this document, but in short, just AIA.

What it is?

According to part 3 of Art. 55 of the Civil Code of the Russian Federation for objects, it is necessary to submit a list of documents, including a conclusion on compliance issued by the bodies of the GOS.

If someone gives you permission to enter in the absence of this document, then he will be held administratively liable under Part 4 of Art. 9.5 of the Code of Administrative Offenses of the Russian Federation. They can also appeal your permission to enter and cancel it.

This document is issued by the GOS bodies based on the results of implementation during construction. reconstruction of the state construction supervision in accordance with the requirements of Art. 54 GK RF. If you did not notify the GSN authorities about the start of construction and the state construction supervision was not carried out at your facility, then you will not be issued a conclusion on compliance. You will have to put the facility into operation in a judicial proceeding, appointing a forensic examination of the work performed, etc.

What does the conclusion look like?

Click on the picture to enlarge

Usually, an act of final inspection and an order on approval of the conclusion are attached to the conclusion. The form of conclusion is given in RD 11-04-2006.

How to get it

To obtain this document, the developer must take the following steps

  • submit to the GOS authorities
  • if necessary file , subject to verification
  • submit on time
  • upon completion of construction, submit to the GOS bodies
  • after receiving the act of the final inspection without comments, apply for the issuance of an opinion ()

Also, the procedure for obtaining this document is described in detail in RD 11-04-2006.

If you have any questions feel free to ask them in the comments. See you soon.

P.p.s. Friends, I also want to recommend you "Generator and additional documentation - Generator-ID" from the site ispolnitelnaya.com. The program is so simple and effective that it will save a lot of time. I advise everyone to take a look!!!

Application №3

ACT

on the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the design documentation.

"__" _________ 200g.

1. Representatives of the developer

customer _______________________________

(organization, position, full name) lbuilding contractor (contractor)

(organization, position, full name)

2. Design documentation for construction has been developeddesign organization _______________

(name of design organization)
The construction was carried out according to the project _

(series, project code)

approved ____________________________________________________________________________

(name of the body that approved the project, date)

3. Permission to build an object______________________________________

(number, date of issue)
4. Completed construction, reconstruction, overhaul
capital construction object _____________________________________________________

(Object name)

has the following indicators:


Name of indicator

unit of measurement

By project

actually

1. General indicators of the facility being commissioned

Building volume - Total

including the above ground

total area

Square built-inattached premises

Number of floors

things

2. Non-residential objects

Non-industrial facilities (schools, hospitals,

kindergartens, objects of culture, sports, etc.)

Number of seats Number of visits Capacity

Other indicators

Production facilities

Power Performance Length

(other indicators)foundation materialswall materials floor materials roof materials




Application №3

3. Housing construction objects

Total area of ​​residential premises (for excluding balconies, loggia, veranda terraces)

Number of floors

things

Number of sections

sections

Number of apartments

Total

Including:

1-room

2-room

3-room

4-room

more than 4 rooms

pieces/m²

pieces/m²

pieces/m²

pieces/m²

pieces/m²

pieces/m²

Total area of ​​residentialpremises (taking into accountbalconies, loggias, verandas and terraces)

Foundation materials

Wall materials

Floor materials

Roof materials

4. Construction cost

Construction cost

object - total

including

construction and assembly

works

thousand rubles

thousand rubles

5. Additional information

Based on the information provided

parameters of the capital construction object _____________________________________________

(Object name)

comply with the approved project documentation.

Applications:

Representatives of the developer

Representatives of the customer

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

representatives of the personbuilding

"____" ____________ 20__

___________________________

(signatures, full name)

M.P.




Application No. 4

ACT

on the compliance of the parameters of the constructed, reconstructed, repaired capital construction facility with the technical conditions for the operation of engineering and technical support networks.

"__" _________ 200g.

(developer, or attracted by the developer or customer on the basis of

___________________________________________________________

(organization, position, full name)


present certificate of completed construction ________________________________________

_______________

(Object name)

2. The construction was carried out by the contractor who completed ___________________

(specify type of work)

and its subcontractors________________________________________________________

(name of company)

performing

(specify types of work)

design organizations____________________________________________________________ _________

_______________________________________________________

(number, date of issue)
___________________________________________

(project series)

approved by ________________________________________________________________

documentation

Title of the document

Date of preparation

Note

according to the acts.

Title of the document

Date of preparation

Note

8. Seasonal work (when the deadlines for their implementation are postponed) according tosidewalks, utility, playgrounds and sports grounds, as well as finishing

Types of jobs

unit of measurement

Scope of work

Period of execution

Application No. 4

9. More information ___________________________________________________________

Based on the information provided

Capital construction object __________________________________________

(Object name)

rules).

Applications:

representatives of the personbuilding

(signature, full name) m.p.

* - the item is filled in for capital construction projects that are notthe requirements of paragraph 1 of Article 54 of the Town Planning Code of the Russian Federation, and in relation towhich do not require the issuance of a conclusion on the conformity of the constructed, reconstructed, repaired capital construction object documentation.


Application №2

ACT

on the conformity of the constructed, reconstructed, repairedcapital construction object to the requirements of technical regulations(norms and rules).

"__" _________ 200g.

1. Representative (representatives) of the person carrying out the construction
(developer, or attracted by the developer or customer on the basis of
contract, an individual or legal entity that meets the requirements
legislation of the Russian Federation applicable to persons
constructing) _______________________________________________________

____________________________________________________________________________________________

(organization, position, full name)

Guided by the executive and production documentation, compiled
present certificate of completed construction _________________________________________

____________________________________________________________________________________________

(Object name)

2. The construction was carried out by the contractor who performed_ _________________

__________________________________________________________________________________________ __

(specify the type of work )
and his subcontractors organizations __________________________________________________

(name of company) performing

(specify types of work)

3. Design documentation for construction has been developed
design organizations___________________ ________________ _________________________

(name of design organizations)

4. Building permit__________ _______________________________________________________________

(number, date of issue)

5. The construction was carried out according to the project___________________ _______________

(project series)
approved _______________________________________________________________________

(name of the body that approved the project)

6*. The following production and executive documentation

Title of the document

Date of preparation

Note

7*. The equipment installed at the facility complies with the project andaccepted after individual tests and complex tests according to the acts.

Title of the document

Date of preparation

Note

8. Seasonal work (if the deadlines for their implementation are postponed) according tolandscaping, top coating of access roads to buildings,sidewalks, utility, playgrounds and sports grounds, as well as finishingelements of building facades must be completed and handed over to the investor(to the user) in accordance with the procedure established by the norms within the following terms:

Types of jobs

unit of measurement

Scope of work

Period of execution


made in accordance with the requirements of technical regulations (standards rules).

Applications:

representatives of the person,building

* - the item is filled in for capital construction projects that are not are subject to state construction supervision in accordance withthe requirements of paragraph 1 of Article 54 of the Town Planning Code of the Russian Federation, and in relation to which do not require the issuance of a conclusion on the conformity of the constructed, reconstructed, repaired capital construction object requirements of technical regulations (norms and rules) and design documentation.


ACT

acceptance of the capital construction object.

Customer Representative_______________________________________________________________

_________________________________________________________________________________________

(organization, position, full name)

Representative of the person carrying out the construction (contractor) ___________________

________________________________________________________________________________________

Representative of the design organization _______________________________________________

___________________________________________________________________________

(organization position, full name)

Representative of the organization carrying out technical supervision _____________________

___________________________________________________________________________

(organization position, full name)

Representative of the organization exercising architectural supervision ____________________

__________________________________________________________________________________________

(organization position, full name)

Representative of the operating organization ____________________________________

__________________________________________________________________________________________

(organization position, full name)

have drawn up this Act to the effect that_______________________________________________ ____

(name of contractor)

Completed construction, renovation,
overhaul of a capital construction facility______________________

_____________________________________________________________________________________

(name of object, address)

project ________________________________________________________________

(name of design organization, project code)
in accordance with the requirements of the contract contracts ___________________________________

(number, date)

and handed over, and ____________________________________________________________

(name of the customer organization)

accepted the specified object.

Operating organization_______________________________________________ ____


Applications:

Representatives of the developer

Representatives of the customer

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

representatives of the personbuilding (contractor)

Representative of the design organization

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

Technical Supervision

"____" ____________ 20__

"____" ____________ 20__

___________________________

___________________________

(signatures, full name)

M.P.

(signatures, full name)

M.P.

Operating organization

"____" ____________ 20__

___________________________

(signatures, full name)

M.P.


2022
mamipizza.ru - Banks. Contributions and deposits. Money transfers. Loans and taxes. money and state